South Dublin County Council N7 <strong>Newlands</strong> <strong>Cross</strong> <strong>Upgrade</strong><br />

Environmental Impact Statement<br />

Arup Consulting Engineers<br />

4.3 Scheme Construction<br />

4.3.1 Introduction<br />

Construction of the scheme can be divided into the following principal activities:-<br />

• Construction of the temporary traffic diversions to the N7;<br />

• Construction of the overpass structure;<br />

• Construction of the approach embankments and road pavement to the overpass structure;<br />

• Construction of the on (merge) and off (diverge) slip roads from the N7 mainline;<br />

• Alterations to the Fonthill Road South and the Belgard Road on the approach to the<br />

junction;<br />

• Reinstatement and landscaping of the scheme.<br />

The scheme construction is estimated to take approximately 22 months to complete. It is<br />

anticipated that approximately 100 people could be employed on the scheme construction<br />

works.<br />

The method of procurement for the project will adopt the new Government Form of<br />

Construction Contract for Public Works.<br />

An outline construction method has been developed indicating feasible temporary traffic<br />

arrangements to ensure that the scheme can be built within the site constraints, and this<br />

methodology is illustrated in figures 4.8 to 4.14.<br />

The Contractor for the works will be contractually bound within the contract for the works by<br />

any conditions arising from the site constraints, the recommendations of the <strong>EIS</strong>, the<br />

Employer’s Requirements for the project, any modifications that may be imposed on the<br />

scheme by An Bord Pleanála and all Statutory Regulations.<br />

Before the commencement of construction, the Employers Representative will review and<br />

accept the Contractor’s programme and the proposed method of construction. The method of<br />

construction will include specific details on how the works will be undertaken and how the<br />

environmental objectives or Statutory Regulations will be met.<br />

This section provides an outline of the general activities and issues associated with the<br />

construction of the proposed scheme including:-<br />

• Construction constraints;<br />

• Construction programme, staging and working hours;<br />

• Construction compound;<br />

• Generation, reuse and disposal of excavated material;<br />

• Construction traffic and access;<br />

• Preparatory works;<br />

• Public traffic management;<br />

• General construction methods.<br />

4.3.2 Construction Constraints<br />

The proposed scheme will be constructed in a manner which will minimise, as much as<br />

possible, any disturbance to the local residents and road users. To minimise inconvenience to<br />

the road user, three-way traffic flow will be maintained along the N7 and all existing traffic<br />

movements at the junction will be facilitated within the proposed overall temporary traffic<br />

December 2007 Page 74