12.07.2015 Views

Technical Manual: Conduits through Embankment Dams (FEMA 484)

Technical Manual: Conduits through Embankment Dams (FEMA 484)

Technical Manual: Conduits through Embankment Dams (FEMA 484)

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

ContentsB-33 Aerial view of Como Dam, Montana ............................B-34B-34 Installing the steel pipe slipliner within the existing outlet worksconduit ....................................................B-35B-35 A well designed siphon was to be installed <strong>through</strong> the dam crest ..... B-37B-36 A man-entry inspection of this 60-inch CMP noted seepage and extensive loss of embankment soil at two locations ................. B-39B-37 Erosion scarp on downstream slope of the embankment dam at the location of the overtopping of the dam crest . . . . . .................B-42B-38 Excavation of the controlled breach in the embankment dam ........ B-43B-39 Completion of the initialization of the breach in the embankment dam .......................................................B-43B-40 Deepening of the initial breach channel ..........................B-44B-41 Idealized cross section of Hernandez Dam .......................B-46B-42 Settlement of the outlet conduit at Hernandez Dam ................ B-48B-43 Lake Darling Dam outlet works discharge, circa 1990 .............. B-50B-44 A cross section with a profile of the outlet works and design cross section of Lake Darling Dam................................... B-51B-45 Grouting operations within the conduit ..........................B-53B-46 Aerial view of the breached Lawn Lake Dam and downstream floodplain ..................................................B-55B-47 Right side of the breached Lawn Lake Dam.......................B-55B-48 Left side of the breached Lawn Lake Dam........................B-55B-49 The pipe joints separated when foundation movement occurred duringconstruction of the embankment dam. ..........................B-58B-50 Loveton Farms Dam failure as viewed from upstream. Note that the walls of the failure area are nearly vertical. The construction recordsindicate that a large portion of the embankment dam was placed priorto installation of the CMP .....................................B-61B-51 Loveton Farms Dam after failure as viewed from the downstream end of the 78-in diameter CMP spillway. Note that one of the antiseepcollars, which were about 14 feet square, is visible in the breach ...... B-61B-52 The failed embankment dam was repaired with a new 78-in diameter CMP spillway. However, soon after reconstruction, this failed joint wasdiscovered at the upstream end of the pipe near the riser. A large voidwas also observed in the adjacent embankment fill. Note the o-ringgasket has been displaced from the joint.......................... B-62B-53 Existing 6-foot diameter elliptical conduit . . . . . . . .................B-64B-54 The embankment dam was constructed with antiseep collars ......... B-67B-55 When the pool level of this embankment dam was only about 2 to 3 feetdeep, flow along the outside of the CMP resulted in loss of the adjacentsoils .......................................................B-68B-56 Sinkhole in the dam crest the night of December 11, 1996 . .......... B-70B-57 View of upstream dam crest nearing completion of breach ........... B-71B-58 Pablo Dam nearing completion.................................B-75xxvii

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!