4. Installation<br />

After the upper section has been set to its final elevation and<br />

slope, it is important to note the following:<br />

• Cobble stone / pavers installation<br />

In the case that the upper section and cover will be installed<br />

in a stone / paver surface, it is important that the top of the<br />

upper section is installed approx 2 cm higher than that of the<br />

pavers. When the cobble stones are compacted the upper<br />

section (with the cast iron manhole cover installed and bolted<br />

tight) should also be compacted until it is level with the<br />

surrounding stones<br />

• Installation in traffic areas<br />

In the case that the upper section and cover will be installed<br />

in a surface which is to handle Class D (40.0 metric ton load<br />

classes), a 18cm thick, 2m x 2m B25 concrete load distribution<br />

plate must be poured around the upper section. The concrete<br />

support plate should be steel re-enforced and comply<br />

with any local regulations. A drawing of this load support plate<br />

is available from KESSEL upon request.<br />

• Others<br />

In some instances it may be required that the lower section<br />

of the upper section (in which the cast iron manhole is installed)<br />

be sawed off in order to obtain the correct installation<br />

depth. This cut should be made as evenly as possible and<br />

any remaining loose edges should be filed away (deburring).<br />

The included manhole cover removal key as well as the<br />

User´s Manual for the pumping system should be stored in<br />

a protected dry area in the vicinity of the control unit.<br />

Installation depths<br />

Possible installation depths<br />

KESSEL – Pumpstation Aqualift F in System 1000 Inspection Chamber<br />

Installation depths from 1.63 to 5.13 meters<br />

KESSEL – Pumpstation Aqualift F in System 800 Inspection Chamber<br />

Installation depths from 1.46 to 1.96 meters<br />