14.08.2013 Views

environmental statement - Rotherham's Online Application for ...

environmental statement - Rotherham's Online Application for ...

environmental statement - Rotherham's Online Application for ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

2.26 Tracks between turbines are required during the operational period of the<br />

wind farm to allow <strong>for</strong> maintenance operations, particularly the<br />

replacement of turbine/electrical components if required.<br />

Crane Pads<br />

2.27 Two cranes would be required during the erection of each turbine, typically<br />

a 500 to 650 tonne crane and a smaller 100 to 250 tonne tailing crane. To<br />

provide stable, firm ground <strong>for</strong> cranes to stand on during the installation of<br />

turbines, hard-standing areas would be laid down adjacent to the<br />

foundation. These would be suitable <strong>for</strong> the outriggers of the respective<br />

cranes, leading to an area of approximately 20m by 40m in total.<br />

Typically, construction of the hard-standing areas would be similar to the<br />

construction of the site tracks, with the top 300mm of topsoil being stripped<br />

and stored adjacent to the sites, with the remaining topsoil removed down<br />

to the hard substrate. Geotextile material would be laid down and stone<br />

laid on top to a depth required <strong>for</strong> adequate bearing of the crane<br />

outriggers. The crushed stone would be sourced from local quarries.<br />

Following completion of the construction works, the crane hardstandings<br />

shall be left in-situ to allow any extraordinary maintenance such as major<br />

component replacement, and to also support cranes during eventual<br />

decommissioning. Following the commissioning of the site, however, the<br />

pads would be reinstated with the original topsoil replaced over the load<br />

bearing material and allowed to regenerate naturally. Drawing<br />

HJB/681/PA11 illustrates an indicative crane pad and its relationship to a<br />

turbine.<br />

On-Site Cabling<br />

2.28 The wind turbines to be used at the Penny Hill site would typically produce<br />

electricity at 690-1000 Volts. This would pass through a trans<strong>for</strong>mer<br />

typically located within the nacelle, the base of the tower or in a cabinet<br />

outside the tower, be<strong>for</strong>e being connected into the wind farm underground<br />

collection circuitry.<br />

2.29 The wind turbines would be connected to the on-site metering and control<br />

building and substation via 11 kV or 33kV underground cables placed in<br />

trenches. The cables would generally follow the route of the on-site tracks<br />

as described above. The route would be marked above ground with<br />

clearly identified posts, spaced at suitable intervals along the length. In all<br />

cases, the cables would be buried to a depth of approximately 1m.<br />

Rein<strong>statement</strong> would be in line with the general methods described<br />

previously (i.e. re-laying the previously stripped subsoil and topsoil over<br />

the top of the cable trench).<br />

2.30 Separate communication cables and earth tapes would also be laid in the<br />

trench. Cables would be laid in sand <strong>for</strong> protection, with warning<br />

tapes/boards placed above high voltage cables to mitigate the risk of<br />

unintentional excavation. Where trenches are located on downhill<br />

16<br />

Penny Hill Wind Farm<br />

Environmental Statement

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!