Rein<strong>statement</strong> around turbines;<br />

Construction of grid connection;<br />

Commissioning and testing of turbines; and<br />

Site rein<strong>statement</strong> and restoration.<br />

5.8 Many of the operations outlined above will be undertaken concurrently in<br />

order to minimise the overall duration of the construction phase of the<br />

proposed development. A working programme <strong>for</strong> the construction phase<br />

is depicted on Drawing HJB/681/PA22.<br />

5.9 Construction periods will be restricted to the following:<br />

Monday to Friday: between 08:00 – 18:00;<br />

Saturdays: between 08:00 - 13.00; and<br />

Sundays and Bank Holidays: no work.<br />

5.10 The only exception to the above would be <strong>for</strong> the delivery of abnormal<br />

loads requiring police escort.<br />

5.11 In the case of turbine delivery and construction periods working hours will<br />

be restricted to:<br />

Monday to Friday: between 08:00 – 22:00;<br />

Saturdays: between 08:00 – 22:00<br />

Sundays and Bank Holidays: No work<br />

5.12 In the case of turbine commissioning working hours will be restricted to:<br />

Monday to Sunday (Including Bank Holidays) 08:00 – 22:00<br />

5.13 In the event that any other work needs to take place outside of these<br />

periods, this will be agreed in advance with the local planning authority<br />

and local residents will be notified.<br />

5.14 As stated above, construction activities will be undertaken in accordance<br />

with an EMP <strong>for</strong> the site. The aims of the EMP are to provide guidance on<br />

good working practices on site to minimise the potential impacts to soil,<br />

geology, hydrology and hydrogeology resulting from the construction of the<br />

wind farm. Additional procedures will be developed to cover ecological<br />

and noise impacts. Further details on the EMP are included in Section 16<br />

of this ES and the draft Penny Hill EMP is contained in Appendix 12.<br />

42<br />

Penny Hill Wind Farm<br />

Environmental Statement