noise <strong>of</strong> more than thirty (30) decibels beyond the Property line may also be performed<br />

between the hours <strong>of</strong> 7:00 a.m. to 8:00 a.m. and 6:00 p.m. to 7:00 p.m. Monday through<br />

Friday, and 8:00 a.m. to 9:00 a.m. and 5:00 p.m. to 6:00 p.m. Saturday. Notwithstanding<br />

the foregoing, pursuant to SMMC Section 4.12.110(e), Developer has the right to seek a<br />

permit from the <strong>City</strong> authorizing construction activity during the times otherwise<br />

prohibited by this Section. The Parties acknowledge and agree that, among other things,<br />

after hours construction permits can be granted for concrete pours.<br />

3.3 Outside Building Permit Issuance Date. If Developer has not been issued<br />

a building permit for the Project by the “Outside Building Permit Issuance Date” (defined<br />

below), then on the day after the Outside Building Permit Issuance Date, without any<br />

further action by either Party, this Agreement shall automatically terminate and be <strong>of</strong> no<br />

further force or effect. For purposes <strong>of</strong> clarity, if Developer has not been issued a<br />

building permit for the Project by the Outside Building Permit Issuance Date, the <strong>City</strong><br />

shall not be required to pursue its remedies under Section 11.4 <strong>of</strong> this Agreement, and<br />

this Agreement shall, instead, automatically terminate. “Outside Building Permit<br />

Issuance Date” means the date that is the last day <strong>of</strong> the thirty-sixth (36 th ) full calendar<br />

month after the Effective Date; provided that the Outside Building Permit Issuance Date<br />

may be extended by applicable Excusable Delays and otherwise in accordance with the<br />

remainder <strong>of</strong> this paragraph. If the approval by the ARB <strong>of</strong> the Project design does not<br />

occur within four (4) months <strong>of</strong> the submittal by Developer to the ARB <strong>of</strong> the Project<br />

design, then the Outside Building Permit Issuance Date shall be extended one month for<br />

each additional month greater than four that the final ARB approval is delayed. At any<br />

time before the last day <strong>of</strong> the thirty-sixth (36 th ) full calendar month after the Effective<br />

Date (the "Extension Notice Date"), Developer may deliver written notice to the<br />

Planning Director, requesting an extension <strong>of</strong> the Outside Building Permit Issuance Date<br />

for an additional twelve (12) months. The Outside Building Permit Issuance Date may be<br />

administratively extended not more than one (1) time for an additional twelve (12)<br />

months.. The Planning Director may grant such extension if Developer can demonstrate<br />

substantial progress has been made towards obtaining a building permit and show<br />

reasonable cause why Developer will not be able to obtain the building permit for the<br />

Project by the initial Outside Building Permit Issuance Date and can demonstrate that:<br />

(a) the condition <strong>of</strong> the Property will not adversely affect public health or safety and (b)<br />

the continued delay will not create any unreasonable visual or physical detriment to the<br />

neighborhood.<br />

3.4 Construction Period. Construction <strong>of</strong> the Project shall be subject to the<br />

provisions <strong>of</strong> SMMC Section 8.08.070.<br />

3.5 Damage or Destruction. If the Project, or any part there<strong>of</strong>, is damaged or<br />

destroyed during the term <strong>of</strong> this Agreement, Developer shall be entitled to reconstruct<br />

the Project in accordance with this Agreement if: (a) Developer obtains a building permit<br />

for this reconstruction prior to the expiration <strong>of</strong> this Agreement and (b) the Project is<br />

found to be consistent with the <strong>City</strong>’s General Plan in effect at the time <strong>of</strong> obtaining the<br />

building permit.<br />

26<br />

F:\RECORDSANDELECTIONSHARE\MEETINGS\WWW\2013\20130514\WORD DOCUMENTS\2013051407-A-2.DOC