TA 4721-PRC: Preparing the Shaanxi-Qinling Mountains Integrated Ecosystem Management Project<br />

<strong>Final</strong> <strong>Report</strong> Appendix 1<br />

Design<br />

Summary<br />

Activities with Milestones<br />

Performance Targets Data Sources/<strong>Report</strong>ing<br />

Mechanism<br />

sensing analysis completed and<br />

stored with operational database<br />

accessible to staff by PY 4<br />

Public education and awareness<br />

program implemented<br />

15 professional job exchanges<br />

Component I: Commercial businesses investing in the management of the Project<br />

Area<br />

1.1 Construction of the botanical garden, exhibition and research buildings, nursery,<br />

temple restoration, access roads, and cable car<br />

Activity (1) Establish specialized gardens by end of 2010<br />

Activity (2) Complete the greenhouse development, paleontology museum, Daoist<br />

temples and historic buildings, and other civil works and infrastructure by end 2009<br />

Activity (3) Complete the cableway by end of 2010<br />

Activity (4) Procurement of office and vehicles by end of 2010<br />

Activity (5) Initial resettlement process to be completed by end of 2008 with process<br />

completed by end of 2012<br />

Activity (6) Training programs to be concluded by end of 2010<br />

Activity (7) Design input to be completed by end of 2008, marketing and education to be<br />

completed by end of 2012<br />

1.2 Hot Springs <strong>Development</strong><br />

Activity (8) Villa construction, restaurant and swimming pool complex, site infrastructure<br />

and design and supervision to be completed by end of 2009<br />

1.3 Shaanxi Animal Rescue Center<br />

Activity (9) Crested Ibis breeding base to be completed by 2009, Panda breeding base<br />

and Animal Rescue Center to be completed by 2010, and Golden Monkey base to be<br />

concluded by 2011<br />

Activity (10) Animal exposition area upgraded to international standards<br />

Activity (11) Design and management contract to be concluded by end 2008, and training<br />

to completed by end of 2009<br />

Component II: Improved livelihoods fro sustainable management of in-situ natural<br />

resources<br />

2.1 Village development planning<br />

Activity (12) Complete 16 VDPs by 2010<br />

Activity (13) Conservation Forestry planting and conservation agriculture by 2012<br />

Activity (14) Small Business development grant awarded by 2012<br />

Activity (15) Home stay tourism operators selected and operational by 2012<br />

Activity (16) Road improvement programs and pathway upgraded by 2012<br />

Activity (17) Grants awarded for social infrastructure by 2012<br />

2.2 In-situ Conservation of Biodiversity<br />

Activity (18) Habitat restoration on LFF land completed for 2000ha by 2012<br />

Activity (19) Endangered Species Management Plan for 5 species by 2012 based on field<br />

research contracts<br />

Component III: Institutions for sustainable management of Qinling Mountain natural<br />

Assumptions<br />

and Risks<br />

Inputs:<br />

Total Project $129.16 ___<br />

million<br />

ADB Loan Inputs $40.0__<br />

million<br />

GEF input $4.27 million<br />

Counterpart funds $ 85.9__<br />

million<br />

Civil Works $63.5<br />

Equipment $9.9<br />

Vehicles $0.6<br />

Materials $5.0<br />

Training $1.3<br />

Surveys $5.1<br />

Specialist Services $1.24<br />

Resettlement $5.5<br />

Design and Supervision $3.7<br />

Total Investment cost $96.4<br />

Total Recurrent $16.2<br />

Total Project Cost $123.2<br />

Interest costs $5.9<br />

Fees $0.1<br />

Total cost to be financed $<br />

129.2 million<br />

5