NRO-MOL_2015
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Chapter XI - BUDGET, DEVELOPMENTAL, AND SCHEDULE PROBLEMS—1965 - 1966<br />
109<br />
and the firm’s “underestimate ‘’ of the time needed to<br />
debug the planned optical test chamber. 15 To eliminate<br />
the first obstacle, Dr. Flax on 4 April asked DDR&E for<br />
authority to proceed with the purchase of the unique<br />
facilities and support equipment needed to develop<br />
the primary optical sensor. Foster quickly approved,<br />
whereupon Flax authorized Martin to sign a contact<br />
with Eastman Kodak and proceed with the necessary<br />
facilities construction. 16<br />
Meanwhile, following the 2 April 1966 management<br />
meeting, the <strong>MOL</strong> Program Office took another critical<br />
look at the firm’s proposed 15 September 1969 first<br />
manned launch. Working back from the first date, it<br />
became clear to <strong>MOL</strong> officials that “only 31 months is<br />
available to EKC,” not the 37 months the firm stated it<br />
would need to deliver the camera optical assembly.<br />
The resulting six months gap would therefore slip the<br />
proposed first all-up launch to April 1970. 17<br />
<strong>MOL</strong> Program officials were thus faced with the fact<br />
that less than eight months after the President had<br />
announced the first manned launch would take place<br />
in late calendar year 1968, it had slipped into calendar<br />
year 1970. This situation was particularly embarrassing<br />
to those OSD and Air Force officials who had recently<br />
testified before Congress. On 23 February 1966, for<br />
example, Secretary Brown told the House Appropriations<br />
Subcommittee: “Our best estimate at this time is that the<br />
first manned flight will not occur prior to mid-1969, which<br />
is a slip of about nine months from what we said last<br />
year.” On 8 March Dr. Foster, also advised the Senate<br />
Armed Services Committee that the first manned launch<br />
would take place “about mid-calendar year 1969.”<br />
Citing the repeated schedule slips in the program,<br />
General Evans on 7 April expressed apprehension to<br />
the <strong>MOL</strong> Director that there might be “a very adverse<br />
effect on the program as a whole and the Air Force’s<br />
management image.” He said that, if the schedule<br />
slipped further—due to the still unresolved funding<br />
problem—the program might not survive “as a manned<br />
reconnaissance system.” He urged steps be taken to<br />
reduce expenses and that all contractors be advised<br />
“that we have a major cost problem, that we need their<br />
assistance, and that they should be creative in exploring<br />
ways of reducing program costs.” 18<br />
The FY 1967 Budget Review<br />
The <strong>MOL</strong> budget was already under intensive study<br />
by Air Force officials. In late December 1965, acting on<br />
news that McNamara intended to limit 1967 program<br />
funding to $150 million, General Schriever ordered a<br />
thorough budget review of financial requirements. He<br />
directed Evans to establish a budget review committee<br />
to meet with top contractor officials to analyze the latter’s<br />
cost proposals for Phase II engineering development. 19<br />
Subsequently, Evans proposed, and Flax approved,<br />
establishment of several task forces and senior cost<br />
review boards.<br />
One task force, headed by Col Robert Walling of the<br />
<strong>MOL</strong> Program Office, consisted of eight officials who<br />
beginning in April 1966 embarked on an intensive review<br />
and evaluation of contractor white financial requirements.<br />
Their results were subsequently submitted to a <strong>MOL</strong><br />
Senior Cost Review Board, chaired by Schriever and<br />
including Evans, Stewart, Yarymovych, Major General<br />
G. F. Keeling and Brig Gen W. E. Carter of Headquarters<br />
AFSC and Major General David M. Jones of NASA. The<br />
second task force, chaired by {the} <strong>NRO</strong> Comptroller,<br />
performed the same kind of review in the black area.<br />
Its membership included three representatives from<br />
the <strong>MOL</strong> Program Office and two from the Office of<br />
Space Systems. 20 In this area General Martin had major<br />
responsibility for compiling the DORIAN payload cost<br />
estimates. However, because Eastman Kodak and<br />
General Electric could not complete their final Phase<br />
II cost estimates by 1 May, Martin’s DORIAN report<br />
(submitted on 22 April 1966) contained only the “best cost<br />
data” and were subject to change when firm contractor<br />
proposals were received. 21<br />
On 29 April, at a meeting of the <strong>MOL</strong> Policy Committee,<br />
General Evans presented the results of the above cost<br />
reviews. He reported there was a substantial difference<br />
between the contractors’ preliminary or interim estimates<br />
($2.6 billion) and the Air Force’s estimate ($1.978 billion)<br />
of program costs. Evans reviewed six different program<br />
options for the committee to consider: two of them would<br />
reduce the number of flights by one or two, with program<br />
costs dropping to either $1.817 billion or $1.714 billion. 22<br />
After the briefing, the Committee directed that an<br />
additional seven-shot schedule—two unmanned flights<br />
in 1969 followed by a first manned flight in December<br />
1969 with fully-qualified DORIAN optics—also be<br />
“costed out.” The Committee recognized the difficulties<br />
in getting early delivery of the first qualified optics<br />
package, but still wished to see the first manned flight<br />
take place in calendar year 1969. Concerning the optics