26.12.2015 Views

NRO-MOL_2015

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Chapter XI - BUDGET, DEVELOPMENTAL, AND SCHEDULE PROBLEMS—1965 - 1966<br />

109<br />

and the firm’s “underestimate ‘’ of the time needed to<br />

debug the planned optical test chamber. 15 To eliminate<br />

the first obstacle, Dr. Flax on 4 April asked DDR&E for<br />

authority to proceed with the purchase of the unique<br />

facilities and support equipment needed to develop<br />

the primary optical sensor. Foster quickly approved,<br />

whereupon Flax authorized Martin to sign a contact<br />

with Eastman Kodak and proceed with the necessary<br />

facilities construction. 16<br />

Meanwhile, following the 2 April 1966 management<br />

meeting, the <strong>MOL</strong> Program Office took another critical<br />

look at the firm’s proposed 15 September 1969 first<br />

manned launch. Working back from the first date, it<br />

became clear to <strong>MOL</strong> officials that “only 31 months is<br />

available to EKC,” not the 37 months the firm stated it<br />

would need to deliver the camera optical assembly.<br />

The resulting six months gap would therefore slip the<br />

proposed first all-up launch to April 1970. 17<br />

<strong>MOL</strong> Program officials were thus faced with the fact<br />

that less than eight months after the President had<br />

announced the first manned launch would take place<br />

in late calendar year 1968, it had slipped into calendar<br />

year 1970. This situation was particularly embarrassing<br />

to those OSD and Air Force officials who had recently<br />

testified before Congress. On 23 February 1966, for<br />

example, Secretary Brown told the House Appropriations<br />

Subcommittee: “Our best estimate at this time is that the<br />

first manned flight will not occur prior to mid-1969, which<br />

is a slip of about nine months from what we said last<br />

year.” On 8 March Dr. Foster, also advised the Senate<br />

Armed Services Committee that the first manned launch<br />

would take place “about mid-calendar year 1969.”<br />

Citing the repeated schedule slips in the program,<br />

General Evans on 7 April expressed apprehension to<br />

the <strong>MOL</strong> Director that there might be “a very adverse<br />

effect on the program as a whole and the Air Force’s<br />

management image.” He said that, if the schedule<br />

slipped further—due to the still unresolved funding<br />

problem—the program might not survive “as a manned<br />

reconnaissance system.” He urged steps be taken to<br />

reduce expenses and that all contractors be advised<br />

“that we have a major cost problem, that we need their<br />

assistance, and that they should be creative in exploring<br />

ways of reducing program costs.” 18<br />

The FY 1967 Budget Review<br />

The <strong>MOL</strong> budget was already under intensive study<br />

by Air Force officials. In late December 1965, acting on<br />

news that McNamara intended to limit 1967 program<br />

funding to $150 million, General Schriever ordered a<br />

thorough budget review of financial requirements. He<br />

directed Evans to establish a budget review committee<br />

to meet with top contractor officials to analyze the latter’s<br />

cost proposals for Phase II engineering development. 19<br />

Subsequently, Evans proposed, and Flax approved,<br />

establishment of several task forces and senior cost<br />

review boards.<br />

One task force, headed by Col Robert Walling of the<br />

<strong>MOL</strong> Program Office, consisted of eight officials who<br />

beginning in April 1966 embarked on an intensive review<br />

and evaluation of contractor white financial requirements.<br />

Their results were subsequently submitted to a <strong>MOL</strong><br />

Senior Cost Review Board, chaired by Schriever and<br />

including Evans, Stewart, Yarymovych, Major General<br />

G. F. Keeling and Brig Gen W. E. Carter of Headquarters<br />

AFSC and Major General David M. Jones of NASA. The<br />

second task force, chaired by {the} <strong>NRO</strong> Comptroller,<br />

performed the same kind of review in the black area.<br />

Its membership included three representatives from<br />

the <strong>MOL</strong> Program Office and two from the Office of<br />

Space Systems. 20 In this area General Martin had major<br />

responsibility for compiling the DORIAN payload cost<br />

estimates. However, because Eastman Kodak and<br />

General Electric could not complete their final Phase<br />

II cost estimates by 1 May, Martin’s DORIAN report<br />

(submitted on 22 April 1966) contained only the “best cost<br />

data” and were subject to change when firm contractor<br />

proposals were received. 21<br />

On 29 April, at a meeting of the <strong>MOL</strong> Policy Committee,<br />

General Evans presented the results of the above cost<br />

reviews. He reported there was a substantial difference<br />

between the contractors’ preliminary or interim estimates<br />

($2.6 billion) and the Air Force’s estimate ($1.978 billion)<br />

of program costs. Evans reviewed six different program<br />

options for the committee to consider: two of them would<br />

reduce the number of flights by one or two, with program<br />

costs dropping to either $1.817 billion or $1.714 billion. 22<br />

After the briefing, the Committee directed that an<br />

additional seven-shot schedule—two unmanned flights<br />

in 1969 followed by a first manned flight in December<br />

1969 with fully-qualified DORIAN optics—also be<br />

“costed out.” The Committee recognized the difficulties<br />

in getting early delivery of the first qualified optics<br />

package, but still wished to see the first manned flight<br />

take place in calendar year 1969. Concerning the optics

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!