26.12.2015 Views

NRO-MOL_2015

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

144 The Dorian Files Revealed: a Compendium of the <strong>NRO</strong>’s Manned Orbiting Laboratory Documents<br />

accept “a fund-governed program” tailored to $228<br />

million in fiscal year 1967, $430 million in fiscal year<br />

1968, “and whatever the approved DoD figure is in FY<br />

1969.” Evans suggested <strong>MOL</strong> officials might consider a<br />

possible fourth option: “...decoupling the optics from the<br />

first manned flight with [the] objective being to provide a<br />

more completely man- rated system when the first- flightqualified<br />

DORIAN package becomes available.” 4<br />

He also recommended the <strong>MOL</strong> Program Office<br />

attempt to resolve several other issues, including<br />

determining the best approach to funding future<br />

contracts (commitment versus an expenditure basis),<br />

obtaining a DX priority for the program , and reforming<br />

<strong>MOL</strong> management. This last subject was a sensitive<br />

one to Evans. For many months he had believed that<br />

existing arrangements—which had black <strong>MOL</strong> contract,<br />

development, management, and financial actions being<br />

accomplished by another Air Force activity—were<br />

ineffective. “The present management structure,” he<br />

said, “is incapable of producing a well-integrated, wellmanaged<br />

large program such as <strong>MOL</strong>.”** 5<br />

Some of the questions posed by Evans were discussed<br />

on 10 March 1967 during a management meeting attended<br />

by Dr. Flax, General Ferguson, and other <strong>MOL</strong> officials<br />

at Andrews AFB. Systems Office personnel briefed them<br />

on proposed funding and schedule revisions which they<br />

had been examining with the contractors. They advised<br />

that, even if a 12-month schedule slip was acceptable,<br />

<strong>MOL</strong> would require additional funds beyond the $500/600<br />

million “Bogeys” proposed by Dr. Flax. If given only $480<br />

million in fiscal year 1968, they foresaw a slip in the first<br />

manned flight of at least 15 months. This discouraging<br />

report was subsequently reviewed by Drs. Foster and<br />

Brown, who asked that new guidance be sent to the <strong>MOL</strong><br />

Systems Office. Future funding, the Office was informed<br />

on 17 March, was to be on “a commitment basis” and, for<br />

planning purposes, totals were not to exceed $480 and<br />

$620 million in fiscal years 1968 and 1969. The Systems<br />

Office was directed to prepare a paper on the impact of<br />

those funding levels for presentation to Pentagon officials<br />

in Washington in April. 6<br />

The <strong>MOL</strong> schedule was reworked by <strong>MOL</strong> Systems<br />

Office personnel. They concluded that the 15-month<br />

slip in the first manned launch constituted “an optimum<br />

program from the standpoint of fund limitations” and<br />

For many months Evans had sought to obtain approval for assignment of a<br />

DX industrial priority to the program. The request was never acted upon.<br />

** Gen Martin, previously opposed to Schriever’s plan for integrated<br />

management, on 20 April 1967 agreed that “division of management<br />

responsibility and authority on the basis of security is totally unworkable.” A<br />

major management reorganization followed, which placed all black contracting<br />

under the <strong>MOL</strong> Systems Office, effective 1 July 1967. [Ltr, Martin to Flax,<br />

Ferguson, 20 Apr 67, subj: Management Responsibilities for the <strong>MOL</strong> Program]<br />

would ease development and hardware integration<br />

problems. However, even if funding was provided on a<br />

commitment rather than an expenditure basis, they saw<br />

the program requiring $518 million in fiscal year 1968.<br />

On 15 April 1967 their conclusions were presented to a<br />

<strong>MOL</strong> management meeting attended by Flax, Ferguson,<br />

Stewart, Bleymaier †† , Martin, Berg, and others. Dr. Flax’s<br />

response was to challenge the cost estimates presented<br />

to him; it was his view that the contractor’s costs were<br />

probably inflated, “at least for the scope of work as<br />

currently defined.” He warned that the projected overall<br />

total <strong>MOL</strong> program cost rise of about half a billion dollars,<br />

if correct, might be “very detrimental” to its future and he<br />

directed the <strong>MOL</strong> Systems Office to take another look at<br />

its cost estimates. 7<br />

The cost figures were subsequently reworked on the<br />

West Coast and forwarded to Flax and Ferguson on 2<br />

May by General Bleymaier and Colonel Heran. In their<br />

message, they stated flatly that the funding levels of<br />

$480/600 million in fiscal years 1968 and 1969 “positively<br />

eliminate any possibility of establishing a realistic<br />

12 month slip program.” Furthermore, those levels<br />

placed in jeopardy their ability to meet a 15-month slip,<br />

particularly if there were additional delays in contract<br />

negotiations over the new schedule and deciding on<br />

deferred items. They said that they had examined all<br />

possibilities and nothing could be further gained by<br />

efforts to hold the program to a 12-month slip. “The<br />

only hope in holding the slip to 15 months,” they said,<br />

“lies in proceeding immediately with the negotiations<br />

of a 15 month schedule slide.’’ The contractors “firm<br />

cost proposals,” based on their detailed analysis of a<br />

15-month slip, indicated a two-year funding need for<br />

$524 and $617 million. Accordingly, the $480 million<br />

fiscal year 1968 funding limitation would produce a $44<br />

million deficit, Bleymaier and Heran further stated that:<br />

If you entertain the possibility of<br />

placing increased emphasis on those<br />

system elements that are critical<br />

technically and schedule wise, you will<br />

effectively reduce fund availability<br />

to continue the orderly development<br />

of the total system. To date, we<br />

have proceeded on a balanced funding<br />

approach with orderly development of<br />

interfaces and testing. To deviate<br />

would seriously impair the systems<br />

approach. Expediting part of the<br />

†† Bleymaier who officially took over as Deputy Director, <strong>MOL</strong> Program, on 1<br />

July 1967, participated in various planning exercises during the spring of 1967.<br />

He was, at this time, serving as Commander, Air Force Western Test Range,<br />

Vandenberg AFB, Calif.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!