NRO-MOL_2015
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
144 The Dorian Files Revealed: a Compendium of the <strong>NRO</strong>’s Manned Orbiting Laboratory Documents<br />
accept “a fund-governed program” tailored to $228<br />
million in fiscal year 1967, $430 million in fiscal year<br />
1968, “and whatever the approved DoD figure is in FY<br />
1969.” Evans suggested <strong>MOL</strong> officials might consider a<br />
possible fourth option: “...decoupling the optics from the<br />
first manned flight with [the] objective being to provide a<br />
more completely man- rated system when the first- flightqualified<br />
DORIAN package becomes available.” 4<br />
He also recommended the <strong>MOL</strong> Program Office<br />
attempt to resolve several other issues, including<br />
determining the best approach to funding future<br />
contracts (commitment versus an expenditure basis),<br />
obtaining a DX priority for the program , and reforming<br />
<strong>MOL</strong> management. This last subject was a sensitive<br />
one to Evans. For many months he had believed that<br />
existing arrangements—which had black <strong>MOL</strong> contract,<br />
development, management, and financial actions being<br />
accomplished by another Air Force activity—were<br />
ineffective. “The present management structure,” he<br />
said, “is incapable of producing a well-integrated, wellmanaged<br />
large program such as <strong>MOL</strong>.”** 5<br />
Some of the questions posed by Evans were discussed<br />
on 10 March 1967 during a management meeting attended<br />
by Dr. Flax, General Ferguson, and other <strong>MOL</strong> officials<br />
at Andrews AFB. Systems Office personnel briefed them<br />
on proposed funding and schedule revisions which they<br />
had been examining with the contractors. They advised<br />
that, even if a 12-month schedule slip was acceptable,<br />
<strong>MOL</strong> would require additional funds beyond the $500/600<br />
million “Bogeys” proposed by Dr. Flax. If given only $480<br />
million in fiscal year 1968, they foresaw a slip in the first<br />
manned flight of at least 15 months. This discouraging<br />
report was subsequently reviewed by Drs. Foster and<br />
Brown, who asked that new guidance be sent to the <strong>MOL</strong><br />
Systems Office. Future funding, the Office was informed<br />
on 17 March, was to be on “a commitment basis” and, for<br />
planning purposes, totals were not to exceed $480 and<br />
$620 million in fiscal years 1968 and 1969. The Systems<br />
Office was directed to prepare a paper on the impact of<br />
those funding levels for presentation to Pentagon officials<br />
in Washington in April. 6<br />
The <strong>MOL</strong> schedule was reworked by <strong>MOL</strong> Systems<br />
Office personnel. They concluded that the 15-month<br />
slip in the first manned launch constituted “an optimum<br />
program from the standpoint of fund limitations” and<br />
For many months Evans had sought to obtain approval for assignment of a<br />
DX industrial priority to the program. The request was never acted upon.<br />
** Gen Martin, previously opposed to Schriever’s plan for integrated<br />
management, on 20 April 1967 agreed that “division of management<br />
responsibility and authority on the basis of security is totally unworkable.” A<br />
major management reorganization followed, which placed all black contracting<br />
under the <strong>MOL</strong> Systems Office, effective 1 July 1967. [Ltr, Martin to Flax,<br />
Ferguson, 20 Apr 67, subj: Management Responsibilities for the <strong>MOL</strong> Program]<br />
would ease development and hardware integration<br />
problems. However, even if funding was provided on a<br />
commitment rather than an expenditure basis, they saw<br />
the program requiring $518 million in fiscal year 1968.<br />
On 15 April 1967 their conclusions were presented to a<br />
<strong>MOL</strong> management meeting attended by Flax, Ferguson,<br />
Stewart, Bleymaier †† , Martin, Berg, and others. Dr. Flax’s<br />
response was to challenge the cost estimates presented<br />
to him; it was his view that the contractor’s costs were<br />
probably inflated, “at least for the scope of work as<br />
currently defined.” He warned that the projected overall<br />
total <strong>MOL</strong> program cost rise of about half a billion dollars,<br />
if correct, might be “very detrimental” to its future and he<br />
directed the <strong>MOL</strong> Systems Office to take another look at<br />
its cost estimates. 7<br />
The cost figures were subsequently reworked on the<br />
West Coast and forwarded to Flax and Ferguson on 2<br />
May by General Bleymaier and Colonel Heran. In their<br />
message, they stated flatly that the funding levels of<br />
$480/600 million in fiscal years 1968 and 1969 “positively<br />
eliminate any possibility of establishing a realistic<br />
12 month slip program.” Furthermore, those levels<br />
placed in jeopardy their ability to meet a 15-month slip,<br />
particularly if there were additional delays in contract<br />
negotiations over the new schedule and deciding on<br />
deferred items. They said that they had examined all<br />
possibilities and nothing could be further gained by<br />
efforts to hold the program to a 12-month slip. “The<br />
only hope in holding the slip to 15 months,” they said,<br />
“lies in proceeding immediately with the negotiations<br />
of a 15 month schedule slide.’’ The contractors “firm<br />
cost proposals,” based on their detailed analysis of a<br />
15-month slip, indicated a two-year funding need for<br />
$524 and $617 million. Accordingly, the $480 million<br />
fiscal year 1968 funding limitation would produce a $44<br />
million deficit, Bleymaier and Heran further stated that:<br />
If you entertain the possibility of<br />
placing increased emphasis on those<br />
system elements that are critical<br />
technically and schedule wise, you will<br />
effectively reduce fund availability<br />
to continue the orderly development<br />
of the total system. To date, we<br />
have proceeded on a balanced funding<br />
approach with orderly development of<br />
interfaces and testing. To deviate<br />
would seriously impair the systems<br />
approach. Expediting part of the<br />
†† Bleymaier who officially took over as Deputy Director, <strong>MOL</strong> Program, on 1<br />
July 1967, participated in various planning exercises during the spring of 1967.<br />
He was, at this time, serving as Commander, Air Force Western Test Range,<br />
Vandenberg AFB, Calif.