25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

128 Piling equipment <strong>and</strong> methods<br />

The procedures to be adopted for avoiding ‘waisting’ or ‘necking’ of the shaft, or the<br />

inclusion of silt pockets <strong>and</strong> laitance layers, are similar to those adopted for bored <strong>and</strong> castin-place<br />

piles <strong>and</strong> are described in the following section of this chapter. Precautions against<br />

the effects of ground heave are described in Section 5.8. Because the casing tube is, in all<br />

cases, driven down for the full length of the pile, it is essential to ensure that the interior of<br />

the tube is free of any encrustations of hardened concrete. Even small encrustations can<br />

cause the concrete to arch <strong>and</strong> jam as the tube is withdrawn. If the reinforcing steel is lifted<br />

with the tube the pile shaft is probably defective <strong>and</strong> should be rejected. Further guidance is<br />

given in CIRIA Report PG8 (3.19) .<br />

3.4.6 The installation of bored <strong>and</strong> cast-in-place piles by<br />

power auger equipment<br />

The employment of a power auger for the drilling work in bored <strong>and</strong> cast-in-place piles<br />

presupposes that the soil is sufficiently cohesive to st<strong>and</strong> unsupported, at least for a short<br />

time. Any upper soft or loose soil strata or water-bearing layers are ‘cased-off’ by drilling<br />

down a casing or pushing the tubes down into the pre-drilled hole by vibrator or the crowd<br />

mechanism on the kelly bar. If necessary, ‘mudding-in’ techniques are used at this stage (see<br />

Section 3.3.8). After the auger has reached the deeper <strong>and</strong> stiffer fine-grained soils, the borehole<br />

is taken down to its final depth without further support, until the stage is reached when<br />

a loosely fitting tube is lowered down the completed hole. This loose liner may be required<br />

for safety purposes when inspecting the pile base before placing the concrete; or if an<br />

enlarged base is required, the lining prevents the clay collapsing around the shaft over the<br />

period of several hours or more required to drill the under-ream. The loose liner may not be<br />

needed for straight-sided piles in weak rocks, or in stable unfissured clays, where there is no<br />

risk of collapse before or during the placing of the concrete. However, if the clays are in any<br />

degree fissured there is a risk of the walls collapsing during concreting, <strong>and</strong> thus leading to<br />

defects of the type shown in Figure 3.40. Lining tubes must be inserted in potentially<br />

unstable soils if a visual inspection is to be made of the pile base. Where it is required to<br />

lower inspection personnel into a shaft (which should be greater than 750 mm diameter)<br />

the requirements of BS 8008: 1996 (safety precautions <strong>and</strong> procedures for the construction<br />

<strong>and</strong> descent of machine-bored shafts for piling <strong>and</strong> other purposes) must be followed.<br />

Particular care is needed if an enlarged base has to be inspected or if concrete spreading has<br />

to be carried out by h<strong>and</strong>. The support can be in the form of a ‘spider’, consisting of a number<br />

of hinged arms mounted on a ring. The assembly is lowered down the shaft with the arms in<br />

a near-vertical closed position. They are then lifted upwards <strong>and</strong> outwards <strong>and</strong> locked in<br />

position to form a cone which is pulled up against the clay surface.<br />

Favourable conditions for stability of the borehole are given by care in setting up the rig<br />

on a firm level base <strong>and</strong> attention to maintenance of verticality. Tilting of the rig or violent<br />

operation of the auger leads to misalignment <strong>and</strong> the need for corrective action by reaming<br />

the sides. ‘Working Platforms for Tracked Plant’ (3.20) provides guidance for the design <strong>and</strong><br />

construction of ground-supported platforms for piling plant, although selection of design<br />

parameters to provide realistic mat thicknesses is still a problem. The requirements for the<br />

safety of operatives should be rigorously followed as detailed in the British Drilling<br />

Association Health <strong>and</strong> Safety Manual (3.21) . Casings protecting open pile boreholes should<br />

extend above ground level <strong>and</strong> should be provided with a strong cover.<br />

The final cleaning-up operation before placing concrete in a bored pile consists of removing<br />

large crumbs of soil or trampled puddled clay from the pile base. Any lumps of clay adhering

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!