25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

514 Ground investigations, contracts <strong>and</strong> pile testing<br />

Piling records. The Engineer <strong>and</strong> the Contractor should agree to the form in which<br />

records should be submitted (see Section 11.3).<br />

Cutting down pile heads. The specification should define whether it is the main contractor’s<br />

or the piling contractor’s responsibility to remove excess lengths of pile projecting above the<br />

nominal cut-off level. The responsibility for cutting away concrete to expose reinforcement,<br />

<strong>and</strong> trimming <strong>and</strong> preparing the heads of steel piles should also be stated.<br />

Method of measurement. The method of measuring pile lengths as installed should be<br />

based on an appropriate st<strong>and</strong>ard, for example, as given in Civil Engineering St<strong>and</strong>ard<br />

Method of Measurement (11.17) or in the ICE Specification, modified as necessary to meet<br />

particular contract circumstances, structures <strong>and</strong> sites. Care is needed to define the length<br />

of pile to be measured (i.e. from cut-off level to pile toe or ground level to toe) <strong>and</strong> to state<br />

that it is the total length of a particular type <strong>and</strong> diameter of pile is to be measured. Credits<br />

for short piles installed <strong>and</strong> extra payment for additional lengths of individual piles are<br />

generally excluded from the st<strong>and</strong>ard methods.<br />

Removal of spoil. The respective responsibilities for the removal of spoil from bored piles,<br />

the removal of cut-off lengths of pile, trimming off laitance <strong>and</strong> ground raised by ground<br />

heave, <strong>and</strong> the disposal of used bentonite slurry should be covered in the specification <strong>and</strong> conform<br />

with the statutory regulations for waste disposal currently in force (see Section 11.2.1).<br />

11.3 Control of pile installation<br />

11.3.1 Driven piles<br />

Control of driven pile operations commences with the inspection <strong>and</strong> testing of the<br />

prefabricated piles before they are driven. Thus timber piles should be inspected for quality,<br />

straightness <strong>and</strong> the application of preservative. The operations of casting precast concrete<br />

piles on site or in the factory should be inspected regularly <strong>and</strong> cubes or cylinders of the<br />

concrete should be made daily for compression testing at the appropriate age. Materials used<br />

for concrete production should be tested for compliance with the relevant st<strong>and</strong>ards. In the<br />

case of steel piles, tests should be made for dimensional tolerances <strong>and</strong> full documentation<br />

of the quality of the steel in the form of manufacturers’ test certificates should be supplied<br />

with each consignment. Welding tests should be made for piles fabricated in the factory or<br />

on site. Full radiographic inspection of welds may be necessary only for marine piles, where<br />

the exposure conditions are severe (see Section 10.4.2). The coating treatments should be<br />

checked for film thickness, continuity, <strong>and</strong> adhesion. Degaussing may be needed to counter<br />

magnetization of the pile heads caused by driving. This can be detrimental to the quality of<br />

welds made for pile extensions. BS EN 288 covers degaussing steel by generating a counteractive<br />

magnetic field when welding is in progress.<br />

The ICE Specification lists the information which should be recorded for each type of<br />

pile; Table 11.2 is a typical compliant form. A separate record should be provided for each<br />

pile <strong>and</strong> records should be signed by the Contractor’s <strong>and</strong> Employer’s representatives <strong>and</strong><br />

submitted daily. Records to comply with EC7, Clause 7.9, are similar to Table 11.2, but<br />

should be provided in two parts according to BS EN 12699 for each displacement pile driven.<br />

Part 1 should give general information on the contract <strong>and</strong> type of pile, methods <strong>and</strong> quality<br />

of materials; Part 2 ‘particular information’ as tabulated in Clause 10 of this st<strong>and</strong>ard for<br />

each pile. ‘As built’ records of piles have to be submitted to the Employer. It is advisable to<br />

keep all records for a period of 5 years after completing the works.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!