25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

132 Piling equipment <strong>and</strong> methods<br />

(3) The falling concrete may jam between the reinforcing bars <strong>and</strong> not flow outwards to the<br />

walls of the borehole. Remedy: Ensure a generous space between the reinforcing bars.<br />

The cage should be stiff enough to prevent it twisting or buckling during h<strong>and</strong>ling <strong>and</strong><br />

subsequent placing of concrete. Widely spaced stiff hoops are preferable to helical<br />

binding. Check that the bars have not moved together before the cage is lowered down<br />

the hole.<br />

(4) Lumps of clay may fall from the walls of the borehole or lining tubes into the concrete<br />

as it is being placed. Remedy: Always use lining tubes if the soil around the borehole is<br />

potentially unstable <strong>and</strong> do not withdraw them prematurely. Ensure that adhering lumps<br />

of clay are cleaned off the tubes before they are inserted <strong>and</strong> after completing drilling.<br />

(5) Soft or loose soils may squeeze into the pile shaft from beneath the base of the lining<br />

tubes as they are withdrawn, forming a ‘waisted’ or ‘necked’ shaft. Remedy: Do not<br />

withdraw the casing until the placing of the concrete is complete. Check the volume of<br />

concrete placed against the theoretical volume <strong>and</strong> take remedial action (removal <strong>and</strong><br />

replacement of the concrete) if there is a significant discrepancy.<br />

(6) If bentonite has been used for ‘mudding-in’, the hydrostatic pressure of the bentonite in<br />

the annulus, which is disturbed on lifting the casing, may be higher than that of the fluid<br />

concrete, thus causing the bentonite to flow into the concrete. This is a serious defect<br />

<strong>and</strong> is difficult to detect. It is particularly liable to happen if the concrete is terminated<br />

at some depth below the top of the ‘mudded-in’ casing. Remedy: Keep a careful watch<br />

on the level <strong>and</strong> density of the bentonite gel when the casing is lifted. Watch for any<br />

changes in level of the concrete surface <strong>and</strong> for the appearance of bentonite within the<br />

concrete. If inflow of the bentonite has occurred the defective concrete must be<br />

removed <strong>and</strong> replaced <strong>and</strong> the ‘mudding-in’ technique must be ab<strong>and</strong>oned.<br />

(7) Infiltration of groundwater may cause gaps, or honeycombing of the concrete.<br />

Remedy: Adopt the techniques for dealing with groundwater in pile boreholes<br />

described in Section 3.4.8.<br />

Further guidance on the installation procedures is given in CIRIA Report PG2 (3.23) .<br />

3.4.7 Installing continuous flight auger piles<br />

CFA piles can be installed in a variety of soils, dry or waterlogged, loose or cohesive, <strong>and</strong><br />

through weak rock. The soil is loosened on insertion of the auger <strong>and</strong> the borehole walls are<br />

supported by the auger flights filled with drill cuttings; bentonite support slurry is not used.<br />

The pile is concreted through a bottom or side exit at the tip of the hollow stem auger (100 or<br />

127 mm bore) using a concrete pump connected by hose to a swivel on the rotary head as<br />

the auger is slowly rotated <strong>and</strong> withdrawn. Soil is brought to the surface on the auger blades.<br />

The concrete flow rate <strong>and</strong> feed pressure are continuously measured at the tip; reinforcement<br />

is pushed or vibrated into the fresh concrete. In order to avoid the problems of flighting <strong>and</strong><br />

polishing (see Section 2.4.2) which reduce pile capacity, reliable instrumentation <strong>and</strong> experienced<br />

operators are essential.<br />

For rotary displacement auger piles the displacement tool, which is mounted at the bottom<br />

of a drill tube, is rotated by the high torque top drive <strong>and</strong> forced into the ground by the<br />

rig crowd thereby compacting the wall of the hole. The pile is concreted through the auger<br />

tip as the tool is rotated out of the hole maintaining the profile. To form the various types of<br />

screw piles, discussed in Section 2.3.5, the thick-flanged continuous auger is screwed into

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!