25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

28 Types of pile<br />

Spacer bolts<br />

Spacer<br />

blocks<br />

Steel angle<br />

spacers<br />

Concrete casting bed<br />

Figure 2.8 Timber formwork for precast concrete piles.<br />

Timber<br />

sheathing<br />

Steel angle bearer<br />

Timber fillet<br />

Holding down<br />

bolt<br />

Folding<br />

wedges<br />

employed. The 89 mm point was machined concave to 12.7 mm depth <strong>and</strong> embedded in a<br />

chilled cast-iron shoe. Flame treatment of the point was needed after casting into the shoe<br />

to restore the hardness lost during this operation.<br />

<strong>Pile</strong>s may be cast on mass concrete beds using removable side forms of timber or steel<br />

(Figure 2.8). The reinforcing cage is suspended from bearers with spacing forks to maintain<br />

alignment. Spacer blocks to maintain cover are undesirable. The stop ends must be set truly<br />

square with the pile axis to ensure an even distribution of the hammer blow during driving.<br />

Vibrators are used to obtain thorough compaction of the concrete <strong>and</strong> the concrete between the<br />

steel <strong>and</strong> the forms should be worked with a slicing tool to eliminate honeycombed patches.<br />

The casting beds must be sited on firm ground in order to prevent bending of the piles during<br />

<strong>and</strong> soon after casting. After removing the side forms the piles already cast may be used as side<br />

forms for casting another set of piles in between them. If this is done the side forms should be<br />

set to give a trapezoidal cross-section in order to facilitate release. <strong>Pile</strong>s may also be cast in<br />

tiers on top of each other, but a space between them should be maintained to allow air to<br />

circulate (Figure 2.9). Casting in tiers involves a risk of distortion of the piles due to settlement<br />

of the stacks. In addition, the piles which are first to be cast are the last to be lifted which is in<br />

the wrong order, since the most-mature piles should be the first to be lifted <strong>and</strong> driven.<br />

Where piles are made in a factory, permanent casting beds can be formed in reinforced<br />

concrete with heating elements embedded in them to allow a 24-hour cycle of casting <strong>and</strong><br />

lifting from the moulds. This method of construction was used by Soil Mechanics Ltd. to<br />

cast prestressed concrete piles at Drax Power Station in Yorkshire (2.7) where the large number<br />

of piles cast (18 500) justified the establishment on site of an elaborate casting yard such<br />

as would be used in a precast concrete factory. The reinforced concrete formwork is shown<br />

in Figure 2.10. This type, which does not have removable side forms, necessitates the<br />

embedment of lifting plugs or loops into the top of the piles.<br />

The layout of the casting yard at Drax is shown in Figure 2.11. The str<strong>and</strong> reels were set<br />

on carriers at one end of the four rows of casting beds, with the winches for tensioning the<br />

str<strong>and</strong> at the opposite end. Each casting bed had five lines of forms. The provision of electric<br />

heating elements enabled the concrete to achieve its release strength of 27.6 N/mm 2 in 40 to<br />

48 hours. An average of 300 piles per week, with a peak of 400 in a week, were manufactured.<br />

Two coats of whitewash were used as a release agent, as it was found that mould oil did not

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!