25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

524 Ground investigations, contracts <strong>and</strong> pile testing<br />

BS EN 1536 advises that the supports or anchorages of a reaction system for pile loading<br />

tests should observe minimum clearances from the test pile (diameter D) as follows:<br />

(a) Kentledge supports: clearance � 3 � D<br />

(b) Bond lengths of vertical anchorages: clearance � 3 � D <strong>and</strong> 3 m<br />

(c) Bond lengths of inclined anchorages: clearance � 5 � D <strong>and</strong> � 5 m<br />

BS EN 12699 for tests on displacement piles <strong>and</strong> EC7-1 are silent on support spacing.<br />

The combined weight of the kentledge <strong>and</strong> reaction girders, or the calculated resistance<br />

capacity of tension piles or cables, must be greater than the maximum jacking force<br />

required. In the case of kentledge loading the combined weight should be about 20% greater<br />

than this force. Cable anchorages or tension piles should have an ample safety factor against<br />

uplift. The former can be tested by stressing the anchors after grouting them in. If there is<br />

any doubt about the uplift capacity of tension piles a test should be made to check the design<br />

assumptions. Increased capacity of tension piles in clays can be obtained by under-reaming<br />

them (see Section 6.2).<br />

The reaction girders <strong>and</strong> load-spreading members should be so arranged that eccentric<br />

loads caused by any lateral movement of the pile head will not cause dangerous sidesway, or<br />

buckling of the girders. Connections should be bolted so that they will not become dislodged<br />

if there is a sudden rebound of load due to the failure of the pile shaft or of the jack.<br />

Similarly the kentledge stack should not be arranged in such a way that it may topple over.<br />

Restraint by a pair of anchors from a single pile to each end of the reaction girder is not<br />

a good practice as it can cause dangerous sidesway of a deep girder. The piles or anchor<br />

cables should be placed in pairs at each end of the girders, as shown in Figures 11.8 <strong>and</strong><br />

11.9. Permanent piles can be used as anchorages for ML tests on working piles but it is<br />

unwise to use end-bearing piles for this purpose when the shaft friction will be low <strong>and</strong> the<br />

pile may be lifted off its seating. When using tension piles special threaded anchor bars<br />

extending above the pile head should be cast into the piles for attachment to the reaction<br />

girders. It is inadvisable to weld such bars to the projecting reinforcing bars because of the<br />

difficulty in forming satisfactory welds to resist the high tensile forces involved.<br />

The hydraulic jack should have a nominal capacity which exceeds by 20% or more the<br />

maximum test load to be applied to the pile. This is necessary in order to avoid heavy manual<br />

pumping effort when nearing maximum load <strong>and</strong> to minimize the risks of any leakage<br />

of oil through the seals. The jacking force on the pile head should be measured by a load<br />

cell or pressure capsule since the pressure gauge fitted to most jacks is not sufficiently accurate,<br />

particularly when working towards the maximum capacity of the jack. However, the<br />

jack should have a pressure gauge mounted on the pumping unit which is calibrated to read<br />

in terms of the force on the ram. This gauge is necessary since the load cell mounted on the<br />

pile head may not be visible from the pumping position. For high-capacity piling tests, much<br />

heavy manual effort is saved by providing a mechanical pumping unit, <strong>and</strong> where CRP tests<br />

are being made a load pacer is a useful addition. The ram of the jack should have a long<br />

travel where piles are being loaded near to the failure condition. This avoids the necessity of<br />

releasing oil pressure <strong>and</strong> repacking with steel plates above the ram as the pile is pushed into<br />

the ground. Equipment is available for monitoring <strong>and</strong> restoring jacking loads at intervals of<br />

only a few seconds (11.20) .<br />

The reaction girders, anchorages <strong>and</strong> jacking arrangements for a 5800 tonne static load<br />

test in Taipei are shown in Figure 11.10.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!