25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

130 Piling equipment <strong>and</strong> methods<br />

require ramming or vibrating. The mix proportions should be such as to ensure compliance<br />

with the requirements regarding strength <strong>and</strong> minimum cement content of BS EN 1536 or<br />

with any special requirements for durability (see Section 10.3.1). A dry mix should be used<br />

for the first few charges of concrete if the pile base is wet. The concrete in the shaft is fed<br />

through a hopper or chute placed centrally over the pile to direct it clear of the sides <strong>and</strong> the<br />

reinforcement. After completing concreting, the lining tubes are withdrawn. If a loose liner<br />

is used inside an upper casing, the former is lifted out as soon as the concrete extends above<br />

the base of the outer tube. A vibrator of the type described in Section 3.1.5 is a useful expedient<br />

for extracting the upper casings used to support soft clays or loose s<strong>and</strong>. The quantity<br />

of concrete placed in the shaft should allow for the outward slumping which takes place to<br />

fill the space occupied by the tube <strong>and</strong> any overbreak of the soil outside it. At this final stage<br />

there is inevitably some laitance which has risen to the top of the concrete. The laitance may<br />

be diluted <strong>and</strong> contaminated with water <strong>and</strong> silt expelled from around the casing as the<br />

concrete slumps outwards to fill the gap. Thus the level of the concrete should be set high<br />

so that this weak laitance layer can be broken away before bonding the pile head onto its cap.<br />

The terms of the contract should make it clear whether or not this removal should be<br />

performed by the piling contractor.<br />

The concrete in a pile shaft may be required to be terminated at some depth below ground<br />

level, for example, when constructing from ground surface level, piles designed to support<br />

a basement floor. It is a matter of some experience to judge the level at which the concrete<br />

should be terminated, <strong>and</strong> it is difficult to distinguish between fluid concrete <strong>and</strong> thick<br />

laitance when plumbing the level with a float. Fleming <strong>and</strong> Lane (3.22) recommend the following<br />

tolerances for all conditions:<br />

Concrete cast under water: �1.5 to �3 m<br />

Concrete cast in dry uncased holes: �75 to �300 mm<br />

Concrete cast in cased holes:<br />

the greater of (a) �75 to � 300 min � cased length/15<br />

or (b) �75 to � 300 mm � [depth to casting<br />

level � 900 mm/10]<br />

The Institution of Civil Engineers Specification for Piling (2.5) specifies casting tolerances<br />

for three conditions of placing concrete in pile boreholes with <strong>and</strong> without temporary<br />

casing. The ground surface or piling platform level is defined as the ‘commencing surface’.<br />

The three conditions refer to a situation where the cut-off level is at a depth Hm below the<br />

commencing surface such that H is from 0.15 to any depth for condition (a) <strong>and</strong> below or<br />

between 0.15 <strong>and</strong> 10 m for (b) <strong>and</strong> (c). The conditions are as follows:<br />

(a) Concrete placed in dry boreholes using permanent casing or cut-off level in stable ground<br />

below base of casing: the casting tolerance in metres is specified to be 0.3 � H/10<br />

(b) Concrete placed in dry boreholes using temporary casing other than as (a) above: the<br />

casting tolerance in metres is specified to be 0.3 � H/12 � C/8, where C is the length<br />

of temporary casing below the commencing surface<br />

(c) Concrete placed under water or a drilling fluid: the casting tolerance in metres is<br />

specified to be 1.0 � H/12 � C/8 where C is the length of temporary casing below the<br />

commencing surface.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!