25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Miscellaneous piling problems 443<br />

procedure on the adjoining piles. Where piles are installed in rows or closely spaced groups<br />

by preloading or ‘pre-testing’ methods, the operation of jacking an individual pile relieves<br />

some of the load on the adjacent piles which have already been installed <strong>and</strong> wedged-up. It<br />

then becomes necessary to replace the jacks <strong>and</strong> re-load these piles, after which the inserted<br />

struts are re-wedged. Alternatively, all the pre-testing jacks can remain in position until<br />

the last pile in the group or row is jacked down. Then all the loads on the jacks are balanced,<br />

the struts installed, <strong>and</strong> the jacks removed. The final operation is to encase the struts <strong>and</strong><br />

pile heads in concrete well rammed-up to the underside of the existing foundation.<br />

Steel tube or box section ‘jacked piers’ such as those manufactured by Atlas Systems <strong>and</strong><br />

A B Chance in the USA <strong>and</strong> Rautoruukki Metform in Finl<strong>and</strong> support the foundation being<br />

underpinned on a steel bracket fixed to the top of the pile section. Diameters range from 60<br />

to 320 mm, provided in short lengths appropriate to the jack stroke, with friction or welded<br />

joints for the thin wall sections <strong>and</strong> threaded joints for 10 mm wall. The bearing capacity of<br />

slender piles will be governed by the buckling resistance in weak soils. Corrosion protection<br />

should be provided.<br />

Where steel sections have to be added by welding during pile jacking to reach the required<br />

stratum or resistance, the alignment <strong>and</strong> welding quality can be difficult to control when<br />

working in constricted spaces excavated under existing foundations.<br />

Whichever system of jacked piles is used, safeguards are needed to avoid a sudden drop<br />

in the ram due to loss of oil pressure. Also care must be taken to restrain the existing<br />

foundation, or the rows of jacks <strong>and</strong> struts, from moving horizontally due to lateral or eccentric<br />

thrusts. Raking shores to the superstructure, strutting of the existing foundation to the walls<br />

of the underpinning pit, or bracings between jacks <strong>and</strong> pile heads can be used to restrain<br />

lateral movement.<br />

The existing columns or walls of the structure to be underpinned can be used to provide<br />

the reaction to jacking if they are sufficiently massive. Niches are cut into the faces of the<br />

structure <strong>and</strong> concrete corbels or brackets are cast into these pockets to form the bearing<br />

members for the jacks, as shown in Figure 9.7. The pairs of jacks must, of course, be<br />

operated simultaneously to avoid applying eccentric loading to the existing structure.<br />

Where H-section piles are used to provide underpinning combined with lateral support to<br />

a deep excavation, as shown in Figure 9.1b, they can be installed by placing them in holes<br />

previously drilled by mechanical auger or, in stable ground, by tripod rigs. If the drill holes<br />

are given continuous support by a bentonite slurry or by casing there should be a negligible<br />

loss of ground around the borehole <strong>and</strong> the installation of the piles is effected with little<br />

noise or damaging vibration. Where it is necessary to use tripod rigs in unstable coarse soils,<br />

there is a risk of loss of ground around the boreholes as described in Section 3.3.7. If there<br />

is such a risk it will be necessary to shore the building temporarily with supports bearing on<br />

the ground outside the zone of subsidence. Below the level planned for the base of the<br />

excavation the space between the pile <strong>and</strong> the borehole is filled with a weak s<strong>and</strong>–cement<br />

mortar. This provides the required passive resistance to lateral loads on the piles <strong>and</strong> allows<br />

the latter to be removed if permitted by the planned sequence of underpinning <strong>and</strong><br />

construction of the permanent work.<br />

Bored piles used in the combined role of underpinning <strong>and</strong> lateral support to the sides of<br />

the excavation can be arranged in a single row (Figure 9.8a) or a double row of abutting<br />

piles, or in a single row of interlocking piles (Figure 9.8b). When they are abutting the system<br />

is known as ‘contiguous piling’ <strong>and</strong> when interlocking as ‘secant piling’. Contiguous<br />

piles are cheaper to install, but because it is impossible to drill the holes in a truly vertical

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!