25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Pile</strong> groups under compressive loading 281<br />

Detrimental effects from heave are not usually experienced when driving piles in<br />

groups in coarse soils. A loose soil is densified, thus requiring imported filling to make<br />

up the subsided ground surface within <strong>and</strong> around the group. Adjacent structures may be<br />

damaged if they are within the area of subsidence. A problem can arise when the first piles<br />

to be installed drive easily through a loose s<strong>and</strong> but, as more piles are driven, the s<strong>and</strong><br />

becomes denser thus preventing the full penetration of all the remaining piles. This problem<br />

can be avoided by paying attention to the order of driving, as described in Section 5.8.<br />

Subsidence due to the loss of ground within <strong>and</strong> around a group in a coarse soil can be<br />

quite severe when bored <strong>and</strong> cast-in-place piles are installed, particularly when ‘shelling’ is<br />

used as the boring method (see Section 3.3.7). The subsidence can be very much reduced, if<br />

not entirely eliminated, by the use of rotary drilling with the assistance of a bentonite slurry<br />

(see Section 3.3.8).<br />

5.8 Precautions against heave effects in pile groups<br />

It will have been noted from Section 5.7 that the principal problems with soil heave <strong>and</strong> the<br />

uplift of piles occur when large displacement piles are driven into clay. In coarse soils<br />

the problems can be overcome to a great extent by using small displacement piles such as<br />

H-sections or open-ended steel tubes. To adopt a spacing between piles of 10 or more diameters<br />

is not usually practical if pile group dimensions are to be kept within economical<br />

limits. Pre-boring the pile shaft is not always effective unless the pre-bored hole is taken<br />

down to the pile base, in which case the shaft friction will be substantially reduced if not<br />

entirely eliminated. Jetting piles is only effective in a coarse soil <strong>and</strong> the problems associated<br />

with this method are described in Section 3.1.9. The most effective method is to re-drive any<br />

risen piles, after driving all the piles in a cluster that are separated from adjacent piles by at<br />

least 12 diameters has been completed.<br />

In the case of driven <strong>and</strong> cast-in-place piles, a permanent casing should be used <strong>and</strong> the<br />

re-driving of the risen casing <strong>and</strong> pile base should be effected by tapping the permanent<br />

casing with a 3-tonne hammer, as described by Brzezinski et al. (5.32) Alternatively, the<br />

‘Multitube’ method described by Cole (5.33) can be used. This consists of providing sufficient<br />

lengths of withdrawable casing to enable all the piling tubes to be driven to their full depth<br />

<strong>and</strong> all the pile bases to be formed before the pile shafts in any given cluster are concreted.<br />

An individual cluster dealt with in this way must be separated from a neighbouring cluster<br />

by a sufficient distance to prevent the uplift of neighbouring piles or to reduce this to an<br />

acceptable amount. On the three sites described by Cole it was found possible to drive piles<br />

to within 6.5 diameters of adjacent clusters without causing an uplift of more than 3 mm to<br />

the latter. This movement was not regarded as detrimental to the load/settlement behaviour.<br />

Cole stated that, although the ‘Multitube’ system required eight driving tubes to each piling<br />

rig, the cost did not exceed that of an additional 2 m on each pile.<br />

Curtis (3.26) states that it is possible to re-drive risen driven <strong>and</strong> cast in-situ piles using a<br />

3-to 4-tonne hammer with a drop not exceeding 1.5 m. The head of the pile should be<br />

protected by casting on a 0.6 m capping cube in rapid-hardening cement concrete.<br />

Cole (5.33) stated that the order of driving piles did not affect the incidence of risen piles<br />

but it did change the degree of uplift on any given pile in a group. Generally, the aim should<br />

be to work progressively outwards or across a group, <strong>and</strong> in the case of an elongated group<br />

from end to end or from the middle outwards in both directions. This procedure is particularly<br />

important when driving piles in coarse soils. If piles are driven from the perimeter towards

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!