25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Ground investigations, contracts <strong>and</strong> testing 509<br />

which are separate from, but operate alongside, the works contract, are now frequently<br />

requested by the Employer, developer or project funders. They provide for liability to a<br />

beneficiary (who may not be the same person as the principal works owner) in respect of<br />

defective performance over a period of time, possibly longer than the statutory defects<br />

period, <strong>and</strong> must be treated with caution by specialist contractors.<br />

Model procedures for piling contracts <strong>and</strong> specifications are given in a publication of the<br />

Institution of Civil Engineers (2.5) for use with the Institution’s st<strong>and</strong>ard forms of contract, but<br />

with provisions for drafting to conform to other forms. Account should also be taken of the<br />

BS EN St<strong>and</strong>ards for execution of special geotechnical works (see Section 2.1).<br />

Building <strong>and</strong> construction works on behalf of government departments are usually carried out<br />

under a form of contract designated GC/WORKS/1, similar to the ICE form. Here the Employer,<br />

advisers <strong>and</strong> designers are termed the ‘Authority’ <strong>and</strong> the supervisory duties of the Engineer are<br />

delegated to the ‘Superintending Officer’. As with the other forms, responsibility for design of<br />

piles may be placed on an independent engineer, the contractor or piling sub-contractor.<br />

There is a growing requirement, particularly for large public sector works, for ‘best value’<br />

procurement, based on ‘partnering’ <strong>and</strong> co-operation using specially prepared documents or<br />

‘charters’. These documents may be based on the st<strong>and</strong>ard forms, particularly the new<br />

Engineering <strong>and</strong> <strong>Construction</strong> Contract (11.16) (part of the Institution of Civil Engineers’<br />

NEC3 suite of contracts) which sets out various st<strong>and</strong>ard options for the Employer <strong>and</strong><br />

Contractor to select: for example, ‘design <strong>and</strong> build’, ‘build-own-operate-transfer’ schemes<br />

or ‘management contract’ forms. One of the main benefits claimed for partnering is that it<br />

provides for a limited list of proven or preferred suppliers <strong>and</strong> sub-contractors who ‘negotiate’<br />

rather than tender competitively to produce the perceived best value for the project<br />

owner/funder. Under these arrangements the specialist sub-contractors are required to enter<br />

into back-to-back agreements with the Employer <strong>and</strong> the other parties which frequently<br />

place additional risk-taking burdens on the specialist. Complex partnering, funding <strong>and</strong><br />

project management arrangements are features of the ‘private finance initiative’ for major<br />

public policy works – for example, hospitals, new rail <strong>and</strong> roadworks.<br />

In the following comments on the responsibilities for piling work it must be understood<br />

that the Engineer is not a party to the contract but acts as the agent for an Employer <strong>and</strong><br />

accepts certain responsibilities on behalf of the Employer under, say, an ICE form of<br />

contract. The Architect or Contracts Administrator acts in a similar way for the Employer in<br />

the JCT form of contract. The term ‘Contractor’ refers to the piling contractor whether as<br />

the main contractor or a nominated or non-nominated sub-contractor.<br />

The Institution of Civil Engineers’ publication provides for four basic types of traditional<br />

contractual arrangement under which piling may be undertaken. These are as follows:<br />

(a) Civil engineering works with an Engineer responsible to an Employer for design <strong>and</strong><br />

supervision<br />

(b) Building works with an Architect responsible to Employer for design <strong>and</strong> supervision<br />

<strong>and</strong> advised by an Engineer<br />

(c) Building or civil engineering works with a Contractor responsible to an Employer (who<br />

has in-house expertise) for design <strong>and</strong> construction <strong>and</strong><br />

(d) Building works with an Architect responsible to an Employer for design <strong>and</strong> supervision<br />

but having no engineering adviser.<br />

The need for the Engineer to define the respective status <strong>and</strong> responsibilities is discussed<br />

below in relation to procedures (b) <strong>and</strong> (c), but it should be noted that an Architect may not

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!