25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

280 <strong>Pile</strong> groups under compressive loading<br />

taken by providing a permanent casing to the piles <strong>and</strong> the concrete was not placed in the<br />

shafts until the pile bases had been re-driven by tapping with a drop hammer to the extent<br />

necessary to overcome the effects of uplift. The measured heave of a cross-section of the<br />

piled area is shown in Figure 5.38. It was found that the soil heave caused the permanent<br />

casing to become detached from the bases, as much as 300 mm of separation being<br />

observed. Heave effects were not observed if the piles were driven at a spacing wider than<br />

12 diameters. This agrees with the curves established by Chow <strong>and</strong> Teh (5.29) which show a<br />

pile head heave of only about 1 mm for a spacing of 12 diameters.<br />

Similar effects were observed by Cole (5.33) . At three sites the heave was negligible at pile<br />

spacings wider than 8 to 10 diameters. Cole observed that uplift was more a function of<br />

the pile diameter <strong>and</strong> spacing than of the soil type or pile length. Where piles carry their load<br />

mainly in end bearing, the effect of uplift is most damaging to their performance <strong>and</strong> on all<br />

sites where soil displacement is liable to cause uplift, precautions must be taken as described<br />

in Section 5.8. Heave is not necessarily detrimental where piles are carried by shaft friction<br />

in firm to stiff clays in which there will be no appreciable subsidence of the heaved soil to<br />

cause negative skin friction to develop on the pile shaft. On a site where a 12-storey block<br />

of flats was supported by driven <strong>and</strong> cast in-situ piles installed in 5 m of firm London Clay<br />

to terminate at the base of a 4 m layer of stiff London clay, about 0.5 m of heave was<br />

observed in the ground surface after 70 piles had been driven within the 24�20 m area of<br />

the block. A pile was tested in an area where 220 mm of heave had occurred. The settlement<br />

at 1300 kN (i.e. twice the working load) was 23 mm, while the settlement at the working<br />

load was only 2.5 mm.<br />

Heaving <strong>and</strong> the development of high pore pressures do not occur when bored <strong>and</strong> castin-place<br />

piles are installed in groups. However, general subsidence around the piled area can<br />

be caused by the ‘draw’ or relaxation of the ground during boring. In soft sensitive clays the<br />

bottom of a pile borehole can heave up due to ‘piping’, with a considerable loss of ground.<br />

These effects can be minimized by keeping the pile borehole full of water or bentonite slurry<br />

during drilling <strong>and</strong> by placing the concrete within a casing which is only withdrawn after all<br />

concrete placing is completed.<br />

Movement of<br />

top of piling tube<br />

in mm<br />

Penetration in m Estimated<br />

ground heave<br />

in mm<br />

400<br />

300<br />

200<br />

100<br />

0<br />

500<br />

250<br />

0<br />

0<br />

2.5<br />

5.0<br />

7.5<br />

10.0<br />

Maximum heave<br />

after pile driving<br />

Net heave after retapping<br />

Number of piles<br />

3<br />

in group 13 12<br />

Glacial<br />

till<br />

12 13 3<br />

Figure 5.38 Observations of heave due to pile driving in clay (after Brzezinski et al. (5.32) ).<br />

Clay

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!