25.12.2012 Views

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

Pile Design and Construction Practice, Fifth edition

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Piling equipment <strong>and</strong> methods 133<br />

the ground with limited crowd applied, although for less cohesive soil more thrust will be<br />

necessary to reach the required depth. The auger is rotated out of the hole as concrete is<br />

pumped through the tip to fill the helical profile of the pile, with only minimal soil being<br />

brought to the surface.<br />

3.4.8 Concreting pile shafts under water<br />

Groundwater in pile boreholes can cause serious difficulties when placing concrete in the<br />

shaft. A depth of inflow of only a few centimetres in, say, 5 minutes which has trickled down<br />

behind the lining tubes or has seeped into the pile base can be readily dealt with by baling<br />

or pumping it out <strong>and</strong> then placing dry concrete to seal the base against any further inflow.<br />

However, larger flows can cause progressive increases in the water content of the concrete,<br />

weakening it, <strong>and</strong> forming excess laitance.<br />

A strong flow can even wash away the concrete completely. The defective piles shown in<br />

Figure 3.41 were caused by the flow of water under an artesian head from a fissured rock<br />

on which the bored piles were bearing after the boreholes had been drilled through a soft<br />

clay overburden. The lined boreholes were pumped dry of water before the concrete was<br />

placed, but the subsequent ‘make’ of water was sufficiently strong to wash away some of the<br />

cement before the concrete has set. The remedial action in this case was to place dry<br />

concrete in bags at the base of the pile borehole <strong>and</strong> then to drive precast concrete sections<br />

into the bags.<br />

In all cases of strong inflow the water must be allowed to rise to its normal rest level <strong>and</strong><br />

topped up to at least 1.0 m above this level to stabilize the pile base. BS EN 1536 requires<br />

that a tremie pipe be used for concreting in submerged conditions (water or slurry); the<br />

tremie bore must be 6 times the maximum size of the aggregate or 150 mm whichever is the<br />

greater. The maximum outside diameter of the pipe including joints should be less than 0.35<br />

times the pile diameter or inner diameter of the casing. The tremie pipe must be clean <strong>and</strong><br />

lowered to the bottom of the pile <strong>and</strong> lifted slightly to start concrete flow. A flap valve should<br />

be used on the end of the tremie pipe rather than a plug or polyethylene ‘go-devil’. During<br />

concreting, the tremie tip must always be immersed in the concrete; 1.50 m below concrete<br />

surface for piles less than 1200 mm diameter <strong>and</strong> 2.50 m for piles greater than 1200 mm. If<br />

immersion is lost during concreting, special precautions are required before placement can<br />

continue; for example, steps must be taken to re-immerse the tremie so that any<br />

contamination will be above the final cut-off level. Other limits for the tremie are given for<br />

concreting barrettes.<br />

Although a bottom-opening bucket is sometimes used instead of a tremie pipe for placing<br />

concrete in pile boreholes, the authors as a general rule condemn this practice. This is<br />

because the crane operator h<strong>and</strong>ling the bucket cannot tell, by the behaviour of the crane<br />

rope, whether or not he has lowered the bucket to the correct level into the fluid concrete<br />

before he releases the hinged flap. If he releases the bucket flap prematurely, the concrete<br />

will flow out through the water <strong>and</strong> the cement will be washed out. On the other h<strong>and</strong>, if<br />

he plunges the bucket too deeply it will disturb the concrete already placed when it is lifted<br />

out. The bottom-dumping bucket method has no advantage over the tremie pipe <strong>and</strong> the<br />

authors would use it only if a pile were large enough for the lowering <strong>and</strong> dumping to be<br />

controlled by a diver.<br />

BS EN 1536 provides guidance for piles formed using the technique known as ‘prepacked<br />

concrete’ for underwater concreting, but it is not recommended here in preference to placing

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!