Relay Removal <strong>and</strong> <strong>Installation</strong><br />

Operation <strong>and</strong> <strong>Maintenance</strong><br />

4. Replace the Display Cover (see “Installing the <strong>SVI</strong> <strong>II</strong> <strong>AP</strong> Display Cover” on<br />

page 140).<br />

Ensure that:<br />

Pneumatic Cover <strong>Installation</strong><br />

The wire is not damaged when feeding it through the housing.<br />

A single O-ring is in place on the wire-sleeve <strong>and</strong> is not damaged.<br />

The four retaining screws are tight <strong>and</strong> torque to 15 in-lb (1.7 N-m).<br />

Inserting the wire sleeve through the housing does not require force.<br />

To install the pneumatic cover:<br />

1. Place the cover over the pneumatic module.<br />

2. Using a 3 mm hex key, install the six screws around the perimeter of the cover <strong>and</strong><br />

torque to 8 in-lb (.9 N-m).<br />

Relay Removal <strong>and</strong> <strong>Installation</strong><br />

Relay <strong>Installation</strong><br />

To remove the pneumatic relay:<br />

1. Using a 3 mm hex key, remove the three screws from around the perimeter of the<br />

relay.<br />

2. Lift the relay off the positioner.<br />

To install pneumatic relay:<br />

1. Place the relay in the designated area on the positioner.<br />

2. Using a 3 mm hex key, install the three screws around the perimeter of the relay.<br />

Make sure that:<br />

1. The five O-rings are seated in the base of the relay <strong>and</strong> are not damaged.<br />

2. The three mounting screws are tight <strong>and</strong> torque to 15 in-lb (1.7 N-m).<br />

NOTE<br />

When you have completed maintenance on the pneumatic<br />

relay it is necessary to reinstall the pneumatic cover. Refer<br />

to on “Pneumatic Cover <strong>Installation</strong>” on page 143.<br />

Adjusting I/P Zero<br />

The I/P Zero is calibrated at the factory prior to shipment. If there is a problem with I/P<br />

zero please contact your representative.<br />

143