Installing the <strong>SVI</strong> <strong>II</strong> <strong>AP</strong> for Double-<br />

<strong>Installation</strong> <strong>and</strong> Set Up<br />

4. Mount take-off bracket to stem block at angle which keeps turnbuckle assembly<br />

parallel to stem (Figure 17) using:<br />

a. For top: two plain 5/16 flat washers, helical spring washer 5/16, two hex nuts 5/<br />

16-18 regular.<br />

b. For bottom: hex nut regular 1/4-20 <strong>and</strong> hex screw 1/4-20 UNC x 22.2 [.88] LG.<br />

Figure 17 Bracket Configuration Strokes .5 - 2.50” <strong>and</strong> 3-6”<br />

5. Ensure the turnbuckle assembly is parallel to the stem <strong>and</strong> the magnets are in the<br />

valve closed position (Figure 18) <strong>and</strong> connect to take-off bracket.<br />

Figure 18<br />

Magnet Position with Valve Closed<br />

41