Airport drainage is again an important<br />
consideration. This alternative<br />
considers the potential to pave over<br />
drainage piping with apron space or<br />
roads as necessary. As there may be<br />
times when access to the drainage<br />
piping is necessary, construction <strong>of</strong><br />
hangars on top <strong>of</strong> the piping is not<br />
considered.<br />
Landside Alternative B considers<br />
locating the ATCT on the north end <strong>of</strong><br />
the <strong>airport</strong>. <strong>The</strong> site considered is<br />
currently occupied by a public parking<br />
lot. As necessary, this parking lot can<br />
be expanded to meet the needs <strong>of</strong> tower<br />
employees. This location is further<br />
discussed later in this chapter.<br />
Advantages: <strong>The</strong> <strong>airport</strong> would have<br />
ownership <strong>of</strong> the entire westside flight<br />
line. More land is available for<br />
development. Separation <strong>of</strong> activity<br />
levels is improved.<br />
Disadvantages: <strong>The</strong> <strong>airport</strong> may run<br />
out <strong>of</strong> land available for development in<br />
the distant future. This likely would<br />
not happen within the next 20 years,<br />
but it could sometime thereafter. This<br />
circumstance should be avoided as<br />
experience at other busy reliever<br />
<strong>airport</strong>s has shown.<br />
LANDSIDE ALTERNATIVE C<br />
Landside Alternative C considers a<br />
more unrestricted development plan. It<br />
provides for property acquisition to the<br />
west <strong>of</strong> Airport Boulevard. This area<br />
encompasses approximately 88 acres.<br />
<strong>The</strong> previously discussed 11 acres to the<br />
southwest <strong>of</strong> the runway along the<br />
4-23<br />
flight line is also considered. As<br />
depicted on Exhibit 4K, this allows for<br />
optimal separation <strong>of</strong> activity levels and<br />
it allows for the development <strong>of</strong><br />
commercial/industrial parcels which<br />
would generate revenue in the form <strong>of</strong><br />
land leases for the <strong>airport</strong>.<br />
A main feature <strong>of</strong> this alternative is the<br />
relocation <strong>of</strong> Airport Boulevard and the<br />
creation <strong>of</strong> a grand entrance to the<br />
<strong>airport</strong> that links directly with the<br />
terminal building area. <strong>The</strong> relocation<br />
<strong>of</strong> Airport Boulevard also creates space<br />
for additional aviation-related parcels<br />
with taxiway access, as well as nonaviation<br />
related business development<br />
parcels.<br />
Utilization <strong>of</strong> the land will easily allow<br />
for the separation <strong>of</strong> activity levels. <strong>The</strong><br />
existing executive hangar apron<br />
immediately to the south <strong>of</strong> the<br />
terminal building is continued to the<br />
west, allowing for the development <strong>of</strong><br />
more hangars. To the west <strong>of</strong> the new<br />
south end T-hangars, a T-hangar<br />
complex is developed. Continued<br />
development along the flight line<br />
includes a large apron area fronted by<br />
large FBO/conventional hangars. <strong>The</strong><br />
remaining flight line is considered for<br />
aviation-related hangar development.<br />
This alternative considers locating the<br />
ATCT immediately to the south <strong>of</strong> the<br />
terminal building. This location is<br />
further discussed later in this chapter.<br />
Advantages: This alternative provides<br />
the <strong>airport</strong> with a development plan<br />
that will meet aviation needs well<br />
beyond the 20-year scope <strong>of</strong> this plan.<br />
As revenue-generating commercial/