Table V-13<br />

2025 Demand and Cost Forecast<br />

Calculation Component<br />

Forecasted Demand<br />

2025 <strong>County</strong> Population (1) 207,014<br />

Adopted LOS Standard (Square <strong>Fee</strong>t per Resident) (2) 1.99<br />

2025 Required Square Footage (3) 411,958<br />

Existing Square Footage (4) 275,704<br />

Additional Square Footage Needed (5) 136,254<br />

Cost per Square Foot (6) $181.65<br />

Total Cost (7) $24,750,539<br />

Programmed funds over the next five years (8) $6,895,000<br />

Remaining funds needed to ac<strong>com</strong>modate 2025 demand (9)<br />

(1) Source: Section II, Table II-1<br />

$17,855,539<br />

(2) Source: Table V-5<br />

(3) Required square footed in 2025, based on existing LOS.<br />

(4) Source: Table V-1<br />

(5) 2025 required square footage (Item 3) less existing square footage (Item 4).<br />

(6) Source: Table V-7<br />

(7) Total cost per square foot multiplied by additional square feet required (Item 5).<br />

(8) Source: Table V-9<br />

(9) Total cost of 2025 demand (Item 7) less the programmed funds over the next five years for<br />

expansion of public buildings (Item 8).<br />

As presented in Table V-13, the <strong>County</strong> will need an additional 136,254 square feet by<br />

2025. This would require an investment of $24.8 million over the next 20 years, $6.9<br />

million of which is already funded.<br />

Estimated Revenues<br />

Based on the growth population projections provided by the IRC Comprehensive Plan<br />

and impact cost per resident calculated in Table V-14, it is estimated that the public<br />

building impact fee revenues will generate $13.9 million through 2025. These<br />

projections are presented in Table V-14. Based on the future demand analysis, the<br />

<strong>County</strong> will need to make an investment of $24.8 million to ac<strong>com</strong>modate the 2025<br />

demand. These figures indicate that the impact fee revenues will need to be used in<br />

conjunction with other revenue sources to ac<strong>com</strong>modate the 2025 demand.<br />

Tindale-Oliver & Associates, Inc.<br />

<strong>Indian</strong> <strong>River</strong> <strong>County</strong><br />

May 2005 V-16 <strong>Impact</strong> <strong>Fee</strong> <strong>Study</strong>