Future Demand Analysis<br />
Future demand analysis for libraries includes projections of 2025 demand for buildings,<br />
land, library materials, and equipment. The additional investment needed to<br />
ac<strong>com</strong>modate 2025 demand is presented in Table VI-21.<br />
Table VI-21<br />
2025 Demand and Cost Forecast<br />
Element<br />
Demand<br />
2025 population (1) 207,014<br />
Building and Land Cost<br />
LOS standard (square feet per 1,000 residents) (2) 580<br />
Necessary building space to ac<strong>com</strong>modate 2025 demand<br />
(square feet) (3) 120,068<br />
Existing building space (square feet) (4) 80,237<br />
Additional building space needed (square feet) (5) 39,831<br />
Building and land cost per square foot (6) $253.53<br />
Total building and land cost (7) $10,098,353<br />
Library Materials Cost<br />
LOS standard (items per 1,000 residents) (8) 3,200<br />
Necessary items to ac<strong>com</strong>modate 2025 demand (9) 662,445<br />
Existing library items (10) 442,436<br />
Additional items needed (11) 220,009<br />
Library material unit cost (12) $44.14<br />
Total library material cost (13) $9,711,188<br />
Equipment Cost<br />
Computer LOS standard (<strong>com</strong>puters per 1,000 residents) (14) 0.7<br />
Necessary <strong>com</strong>puters to ac<strong>com</strong>modate 2025 demand (15) 145<br />
Existing <strong>com</strong>puters (16) 90<br />
Additional <strong>com</strong>puters needed (17) 55<br />
Cost per <strong>com</strong>puter (18) $900<br />
Total <strong>com</strong>puter cost (19) $49,500<br />
Other equipment LOS standard (equipment per 1,000<br />
residents) (20) 0.2<br />
Necessary equipment to ac<strong>com</strong>modate 2025 demand (21) 41<br />
Existing other equipment (22) 32<br />
Additional other equipment needed (23) 9<br />
Cost per other equipment (24) $3,118<br />
Total other equipment cost (25) $28,062<br />
Total equipment cost (26) $77,562<br />
Total buildings, land, materials, and equipment cost (27) $19,887,103<br />
Programmed funds over the next five years (28) $3,340,000<br />
Remaining funds needed to ac<strong>com</strong>modate 2025 demand (29) $16,547,103<br />
Tindale-Oliver & Associates, Inc.<br />
<strong>Indian</strong> <strong>River</strong> <strong>County</strong><br />
May 2005 VI-21 <strong>Impact</strong> <strong>Fee</strong> <strong>Study</strong>