Chapter IX – Commuter <strong>Rail</strong> Services<br />
CHAPTER IX<br />
COMMUTER RAIL SERVICES<br />
This chapter discusses the four existing commuter rail systems in <strong>California</strong>,<br />
including their extension plans: Coaster, Metrolink, Caltrain and ACE. Figure 9A<br />
is a map of existing and potential commuter rail services. Figure 9B is a map of<br />
Southern <strong>California</strong> commuter rail services and Figure 9E is a map of<br />
Northern <strong>California</strong> commuter rail services (shown later in this chapter).<br />
Also discussed are three proposed new commuter rail routes: Ventura and<br />
Santa Barbara Commuter <strong>Rail</strong> Service, Sonoma-Marin-Area <strong>Rail</strong> Transit and<br />
Auburn-Oakland Regional <strong>Rail</strong>.<br />
COASTER COMMUTER RAIL SERVICE<br />
(SAN DIEGO-OCEANSIDE)<br />
PRINCIPAL <strong>2005</strong>-<strong>06</strong> <strong>to</strong> <strong>2015</strong>-<strong>16</strong> ROUTE OBJECTIVES<br />
• Increase ridership and improve mobility in the region.<br />
• Implement timed transfers at various stations and transit centers.<br />
• Initiate and continue implementation of the Cus<strong>to</strong>mer Amenities<br />
Program.<br />
• Implement incremental service increases, if feasible, including:<br />
supplementary mid-day service, reverse peak service, evening service,<br />
and weekend service.<br />
• Construct Oceanside passing track.<br />
• Construct new mainline track between O’Neil and Flores.<br />
• Replace single-track San Diegui<strong>to</strong> River and Santa Margarita bridges<br />
with new two-track concrete bridges.<br />
• Replace other timber bridges with new concrete bridges.<br />
• Upgrade sidings and add second main track segments.<br />
• Continue stabilization of Del Mar Bluffs.<br />
• Construct new parking garage at Oceanside Transit Center.<br />
• Extend platforms at Old Town and Poinsettia Stations.<br />
• Build 500-space parking structure at Solana Beach Station for mixeduse<br />
development.<br />
103