- Page 1 and 2: A MYCLE SCHNEIDER CONSULTING PROJEC
- Page 3 and 4: ACKNOWLEDGMENTS The project coordin
- Page 5 and 6: EBRD Chernobyl Decommissioning/Spen
- Page 7 and 8: TABLE OF FIGURES Figure 1: Nuclear
- Page 9: Foreword by Tomas Kåberger 1 The W
- Page 13 and 14: WNISR classifies 36 Japanese reacto
- Page 15 and 16: AREVA Debacle (new episode). The Fr
- Page 17 and 18: Fukushima Prefecture, 70 percent of
- Page 19 and 20: Introduction A major accident, like
- Page 21 and 22: the past two decades, nuclear power
- Page 23 and 24: There were three exceptions in 2015
- Page 25 and 26: In the first half of 2016, three re
- Page 27 and 28: The current world fleet has a total
- Page 29 and 30: However, many of those projects (48
- Page 31 and 32: Table 2: Reactor Construction Times
- Page 33 and 34: Figure 11: Construction Starts in t
- Page 35 and 36: large-scale new-build. Having asses
- Page 37 and 38: Figure 15: Age Distribution of 164
- Page 39 and 40: timeframe are highly unlikely given
- Page 41 and 42: The IAEA says that, “seven countr
- Page 43 and 44: for four units equaled approximatel
- Page 45 and 46: Over the past year, the design sele
- Page 47 and 48: In Turkey, up to three projects are
- Page 49 and 50: electricity generating company (EÜ
- Page 51 and 52: However, Rosatom highlighted the
- Page 53 and 54: eportedly considering “suspending
- Page 55 and 56: start in 2020 and commercial operat
- Page 57 and 58: floating reactors. 160 There is als
- Page 59 and 60: nonetheless suggested that the proj
- Page 61 and 62:
Nuclear Finances: Corporate Meltdow
- Page 63 and 64:
in the U.S. in 2013 from US$5/MBTU
- Page 65 and 66:
decides not to proceed with Hinkley
- Page 67 and 68:
market capital for renewable energy
- Page 69 and 70:
apply across the whole European mar
- Page 71 and 72:
Supervision and Administration Comm
- Page 73 and 74:
export market to countries such as
- Page 75 and 76:
Conclusion on Corporate Finances Th
- Page 77 and 78:
Sequence and Origin of the Accident
- Page 79 and 80:
a source of carbon dioxide to smoth
- Page 81 and 82:
Figure 29: Cumulative I-131 Concent
- Page 83 and 84:
In total, TORCH-2016 (The Other Rep
- Page 85 and 86:
in Lithuania, Kozloduy units 1 to 4
- Page 87 and 88:
The ISF-2 has been completed, pre-c
- Page 89 and 90:
emove the fuel-containing masses (c
- Page 91 and 92:
around 4.4 m 3 /hour. 270 Therefore
- Page 93 and 94:
Current status of workers The gover
- Page 95 and 96:
The government is aggressively seek
- Page 97 and 98:
(Full-scale Thyroid Screening Progr
- Page 99 and 100:
Costs 315 TEPCO continues to pay co
- Page 101 and 102:
contamination. In all parameters li
- Page 103 and 104:
However, the average thyroid dose i
- Page 105 and 106:
• The Global Energy Assessment 20
- Page 107 and 108:
decisions for the construction of n
- Page 109 and 110:
consecutive year, making up about 7
- Page 111 and 112:
US$43 billion and wind power was US
- Page 113 and 114:
Figure 39: Changes in EU Nuclear, S
- Page 115 and 116:
hydro renewables power generation a
- Page 117 and 118:
Annexes Annex 1: Overview by Region
- Page 119 and 120:
The November 2013 edition of the In
- Page 121 and 122:
its rated power 374 and until 26 Ma
- Page 123 and 124:
ebuilding its Gentilly-2 nuclear at
- Page 125 and 126:
LTEP, released in December 2013, co
- Page 127 and 128:
The U.S. reactor fleet provided 798
- Page 129 and 130:
units had received a license extens
- Page 131 and 132:
the capacity market auctions, the p
- Page 133 and 134:
subsidies already. First, Illinois
- Page 135 and 136:
Conservation (DEC) to deny the plan
- Page 137 and 138:
& 2 in Illinois, Pilgrim in Massach
- Page 139 and 140:
Pending Combined Operating License
- Page 141 and 142:
traditionally been sited, but also
- Page 143 and 144:
projects only after Sanmen-1 ‘suc
- Page 145 and 146:
geographically the nuclear plant th
- Page 147 and 148:
(US$6.6 billion), 546 to as low as
- Page 149 and 150:
work on site in India for six AP100
- Page 151 and 152:
in regulatory safety inspections re
- Page 153 and 154:
2010 Strategic Energy Plan, which h
- Page 155 and 156:
The options for how such targets wo
- Page 157 and 158:
seismic fault line at the site. The
- Page 159 and 160:
The IRRS team concluded that the NR
- Page 161 and 162:
meeting the new regulatory guidelin
- Page 163 and 164:
declared for the reactor and while
- Page 165 and 166:
However, observers saw a “dramati
- Page 167 and 168:
Despite the government’s commitme
- Page 169 and 170:
end of March 2014, unit 1 of Lungme
- Page 171 and 172:
after its license had expired, but
- Page 173 and 174:
The following section provides a sh
- Page 175 and 176:
espectively over one month and two
- Page 177 and 178:
On 22 December 2015, FANC authorize
- Page 179 and 180:
In parallel, Fortum Power has been
- Page 181 and 182:
levels. It now looks plausible that
- Page 183 and 184:
The Hinkley Point C Saga - A French
- Page 185 and 186:
esulting in a loss of market share,
- Page 187 and 188:
for lifetime extensions, before 3/1
- Page 189 and 190:
and coal-fired generation fell back
- Page 191 and 192:
announced in April 2004 that his go
- Page 193 and 194:
nuclear energy, in the form of dire
- Page 195 and 196:
for the £16 billion (US$30 billion
- Page 197 and 198:
to begin operating in 2024. 829 How
- Page 199 and 200:
2019. 839 In December 2015, BKW off
- Page 201 and 202:
assist in financing. 851 Westinghou
- Page 203 and 204:
Hungary has only one nuclear power
- Page 205 and 206:
concluded that when making assumpti
- Page 207 and 208:
in 2012 and 2013. 893 However, the
- Page 209 and 210:
of the MNPP [Medzamor Nuclear Power
- Page 211 and 212:
eactors at the site has been put ba
- Page 213 and 214:
Ukraine has 15 operating reactors,
- Page 215 and 216:
Annex 2: Japanese Nuclear Reactor S
- Page 217 and 218:
Comments WNISR considers that the 1
- Page 219 and 220:
Notes: Top: Air dose at 1 m height
- Page 221 and 222:
Annex 5: Status of Lifetime Extensi
- Page 223 and 224:
Plant Grid Connection Extension App
- Page 225 and 226:
Tomas Kåberger has a MSc in Engine
- Page 227 and 228:
Annex 7: Abbreviations ABWR AEA AEC
- Page 229 and 230:
GPSC GUE/NGL GWEC IAEA IANS IAS ICC
- Page 231 and 232:
PLEC PLEX PPA PRIS PV PWR PXE RAPS-
- Page 233 and 234:
Annex 8: Status of Nuclear Power in
- Page 235 and 236:
Annex 9: Nuclear Reactors in the Wo
- Page 237 and 238:
Country/Reactors Units MWe (net) Co
- Page 239 and 240:
15 Delayed again. A further delay o
- Page 241:
38 Delayed several times. This esti