The following section provides a short overview by country (in alphabetical order).<br />
Belgium Focus<br />
Belgium operates seven pressurized-water reactors and, for many years, had the world’s second<br />
highest share of nuclear in its power mix, behind France. Due to technical issues described below,<br />
it dropped to 47.5 percent in 2014—less than 50 percent for the first time since 1983 693 —and to<br />
37.5 percent in 2015 (the maximum was 67.2 percent in 1986). The nuclear plants generated<br />
24.8 TWh in 2015, another drop of 22.6 percent over 2014, and almost half of their highest output<br />
of 46.7 TWh in 1999. Load factors of individual reactors were obviously particularly low for the<br />
two units plagued by pressure vessel issues (see hereunder) and restarts only towards the end of<br />
the year, Doel-3 with 0.7 percent and Tihange-2 with 4.4 percent (see Figure 48).<br />
Figure 48: Load Factors of Belgian Nuclear Reactors<br />
%<br />
100<br />
Load Factors of Belgian Reactors<br />
(annual 2015 and cumulative, in %)<br />
80<br />
60<br />
40<br />
20<br />
© Mycle Schneider Consulting<br />
0<br />
Doel-1 Doel-2 Doel-3 Doel-4 Tihange-1 Tihange-2 Tihange-3<br />
Load Factor 2015<br />
Load Factor Cumulative<br />
Sources: IAEA-PRIS, MSC, 2016<br />
Legally, the decision does not put into question the nuclear phase-out target of 2025: In January<br />
2003, nuclear phase-out legislation required the shutdown of all Belgium’s nuclear plants after<br />
40 years, so based on their start-up dates, plants would be shut down between 2015 and 2025<br />
(see Figure 49). Practically, however, the new shutdown dates mean that five of the seven reactors<br />
would go offline in the single year of 2025.<br />
Following Fukushima, the phase-out legislation was left in place even though GDF-Suez (now<br />
Engie), that operates all seven PWRs in Belgium through its subsidiary Electrabel, was lobbying<br />
to postpone it via an extension of “at least 10 years”. 694 In December 2013, the phase-out<br />
693 World Bank, quoted in Perspective Monde, see<br />
http://perspective.usherbrooke.ca/bilan/servlet/BMTendanceStatPays?langue=fr&codePays=BEL&codeStat=E<br />
G.ELC.NUCL.ZS&codeStat2=x, accessed 25 May 2015.<br />
694 Gérard Mestrallet, et al., “Nuclear in Belgium: recent developments”, GDF Suez, 4 November 2011.<br />