13.07.2016 Views

CONSULTING

20160713MSC-WNISR2016V2-LR

20160713MSC-WNISR2016V2-LR

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

An overwhelming majority of participants from government, banking sector, academia and<br />

independent expert community concluded during an NGO-convened March 2016 “Technical<br />

Workshop on the Economics of Nuclear Energy” in Johannesburg that there was no viable<br />

financing scheme for newbuild in sight. 370 It is therefore difficult to conceive that the nuclear<br />

newbuild program would fit into South Africa’s strained budget for many years to come.<br />

The five-year target as outlined in the Strategic Plan, is to have completed technology and vendor<br />

selection, the procurement process and to have begun construction of the first unit by 2020; with<br />

connection of the first unit to the grid by 2023 and the second one in 2024. This appears to be an<br />

overly ambitious timeline, by any standards.<br />

The Americas<br />

Argentina operates three nuclear reactors that in 2015 provided 6.5 TWh (a 24 percent<br />

increase over 2014, with Atucha-2 reaching 100 percent power in February 2015) or 4.8 percent<br />

of the country’s electricity (down from a maximum of 19.8 percent in 1990).<br />

Historically Argentina was one of the countries that embarked on an ambiguous nuclear program,<br />

officially for civil purposes but backed by a strong military lobby. Nevertheless, the operating<br />

nuclear plants were supplied by foreign reactor builders: Atucha-1, which started operation in<br />

1974, was supplied by Siemens, and the CANDU (CANadian Deuterium Uranium) type reactor at<br />

Embalse was supplied by the Canadian Atomic Energy of Canada Limited (AECL). After close to<br />

30 years of operation, the Embalse plant was shut down at the end of 2015 for major overhaul,<br />

including the replacement of hundreds of pressure tubes, to enable it to operate for up to 30 more<br />

years. Reportedly, contracts worth US$440 million were signed in August 2011 and at the time,<br />

the work was expected to start by November 2013. 371 According to some reports, the<br />

refurbishment is planned to take about two years, with restart scheduled for March 2018. 372<br />

However, Nuclear Engineering International estimated the project could take up to five years and<br />

cost about US$1.5 billion, warning: “It must be noted, however, that the various Candu<br />

refurbishment projects in Canada (Bruce, Pickering and New Brunswick) have tended to overrun<br />

on both time and budget.” 373<br />

Atucha-2 had been ordered in 1979 and was officially listed as “under construction” since 1981.<br />

Finally, on 3 June 2014, the first criticality of the reactor was announced and grid connection was<br />

established on 27 June 2014. It took until 19 February 2015 for the unit to reach 100 percent of<br />

370 A summary of the workshop with links to the presentations can be found at Henrich Böll Foundation,<br />

Southern Africa, “Workshop Report: The Economics of Nuclear Energy in South Africa”, 9 May 2016, see<br />

https://za.boell.org/2016/05/09/workshop-report-economics-nuclear-energy-south-africa, accessed<br />

1 July 2016.<br />

371 Research and Markets, “Nuclear Power Market in Argentina”, May 2012.<br />

372 SCN Lavalin, “Embalse Nuclear Generating Station Life Extension”, Undated, see<br />

http://www.snclavalin.com/en/embalse-nuclear-generating-station-life-extension, accessed 5 June 2016.<br />

373 NEI, “Argentina—a possible return to new nuclear?”, 15 October 2013, see<br />

http://www.neimagazine.com/opinion/opinionargentina-a-possible-return-to-new-nuclear/, accessed<br />

16 June 2016.<br />

Mycle Schneider, Antony Froggatt et al. 119 World Nuclear Industry Status Report 2016

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!