work on site in India for six AP1000 reactors to be built by Westinghouse and noted the intention<br />

of India and the U.S. Export-Import Bank to work together toward a competitive financing package<br />

for the project (…). Both sides welcomed the announcement by the Nuclear Power Corporation of<br />

India Ltd, and Westinghouse that engineering and site design work will begin immediately and<br />

the two sides will work toward finalizing the contractual arrangements by June 2017”. 564<br />

The relatively vague statement did not excite most financial analysts. Chris Gadomski, a leading<br />

nuclear analyst at Bloomberg New Energy Finance in New York, for example was blunt: “To be<br />

frank, I'll believe it when the check clears (…). There's so many of these deals that, you have to<br />

wait until the pie is completely cooked”. 565 In India, questions have been raised about the cost<br />

competitiveness of these reactors. 566 A recent assessment of the economics of AP1000 reactors by<br />

the Institute for Energy Economics and Financial Analysis found that the costs of generating<br />

electricity at the proposed AP1000 reactors would be at least three and possibly six times the<br />

corresponding cost of setting up solar photovoltaic plants. 567<br />

Japan Focus<br />

For the first time in nearly two years, commercial nuclear reactors began operation in Japan<br />

during 2015. The Sendai-1 reactor restarted on 14 August 568 with Sendai-2 restarting<br />

21 October. 569 In the following months, both reactors generated a total 3 TWh of electricity, or<br />

0.5 percent of the nation’s annual output. This compares with a nuclear share of 1.7 percent of<br />

total electricity in 2013, 2 percent in 2012, 18 percent in 2011, 29 percent in 2010, and the historic<br />

maximum of 36 percent in 1998. The restarts of Sendai were the first reactor operations since<br />

15 September 2013, when Ohi Unit-4 was shut down. 570 Efforts to follow restart of the Sendai<br />

plant, with operation of the Takahama-3 reactor 571 in January 2016, proved short-lived due to an<br />

564 The White House, “Joint Statement: The United States and India: Enduring Global Partners in the 21st<br />

Century”, Press Release, 7 June 2016, see https://www.whitehouse.gov/the-press-office/2016/06/07/jointstatement-united-states-and-india-enduring-global-partners-21st,<br />

accessed 2 July 2016.<br />

565 Tribune-Review, “Westinghouse to Build 6 Nuclear Reactors in India”, 7 June 2016, see<br />

http://triblive.com/business/headlines/10595279-74/deal-india-westinghouse, accessed 2 July 2016.<br />

566 Suvrat Raju, “The Cost of Nuclear Diplomacy,” The Hindu, 20 June 2016, see<br />

http://www.thehindu.com/opinion/op-ed/the-cost-of-nuclear-diplomacy/article8748864.ece, accessed<br />

22 June 2016.<br />

567 David A. Schlissel, “Bad Choice: The Risks, Costs and Viability of Proposed U.S. Nuclear Reactors in<br />

India”, Institute for Energy Economics and Financial Analysis, March 2016, see http://ieefa.org/wp-<br />

content/uploads/2016/03/Bad-Choice_The-Risks-Costs-and-Viability-of-Proposed-US-Nuclear-Reactors-in-<br />

India_-March-2016.pdf, accessed 2 July 2016.<br />

568 WNISR, “32-Year-Old Reactor First to Generate Power in Japan in Nearly Two Years”, 14 August 2015,<br />

see http://www.worldnuclearreport.org/32-Year-Old-Reactor-First-to-Generate-Power-in-Japan-in-Nearly-<br />

Two-Years.html, accessed 17 June 2016.<br />

569 WNISR, “Second Reactor Restarts in Japan”, 22 October2015, see<br />

http://www.worldnuclearreport.org/Second-Reactor-Restarts-in-Japan.html, accessed 17 June 2016.<br />

570 WNISR, “Japan Nuclear Free, Last Operating Reactor Shut Down”, 16 September 2013, see<br />

http://www.worldnuclearreport.org/Japan-Nuclear-Free-Last-Operating.html, accessed 2 July 2016.<br />

571 JAIF, “Kansai EP Starts Up Takahama-3 NPP”, 29 January 2016, see http://www.jaif.or.jp/en/kansai-epstarts-up-takahama-3-npp/,<br />

accessed 17 June 2016.<br />

Mycle Schneider, Antony Froggatt et al. 148 World Nuclear Industry Status Report 2016