Sl.<br />

No.<br />

3<br />

1.<br />

Project Details<br />

North Chennai TPS<br />

St-II<br />

TNEB (Distt.<br />

Thiruvallur)<br />

U-2<br />

Capacity<br />

(MW)<br />

1200<br />

600 08/11<br />

10/11<br />

Date of Sanction : 25.06.2008<br />

Sanctioning <strong>Authority</strong> : Govt. of Tamil Nadu<br />

Org. Est. cost : Rs.271875 Lakh<br />

Commissioning Schedule<br />

Original Actual(A)/ As<br />

now Expected<br />

Syn. COD Syn. COD<br />

Comm<br />

Comm<br />

11/11 08/11<br />

11/11<br />

Latest Est. cost : -<br />

Expd.during 2008-2009 : Rs 21750 Lakh<br />

Expd.during 2009-2010 : Rs 42018 Lakh<br />

Expd.during 2010-2011<br />

(Up to 6/10)<br />

: Rs. 7045 Lakh<br />

Type of fuel : COAL<br />

Date of Main Plant<br />

Order<br />

: 16.08.2008 ( EPC ) on M/s BHEL<br />

Zero Date : 16.08.2008<br />

PRIVATE SECTOR<br />

Melamaruthur TPP<br />

(Coastal Energen)<br />

(Distt. Tuticorin) T.N.<br />

1200<br />

U-1 600 12/2011 12/2011<br />

Date of Sanction : 10.09.2007<br />

Date of financial closure : 02.07.2009<br />

U-2 600 03/2012 03/2012<br />

Org. Est. cost : Rs.480000 Lakh<br />

Latest Est. cost : Rs.480000 Lakh<br />

Expd. during 2007-2008 : Rs. 957 Lakh<br />

Expd. during 2008-2009 : Rs. 16689 Lakh<br />

Cumm.Expd. 2009-2010 : Rs. 50886 Lakh<br />

:<br />

Type of fuel : COAL<br />

Date of Main Plant<br />

Order<br />

Zero Date<br />

Fuel Linkage<br />

Associated Transmission<br />

System<br />

- 99 -<br />

01/12<br />

: 25.02.2009 ( BTG) on M/s Harbin -<br />

- Power Engg. Co. Ltd. China.<br />

: 06.08.2009<br />

: The Company has entered into Fuel Supply<br />

Agreement (FSA) with M/s Coal & Oil, Dubai<br />

for Supply of Entire Coal requirement for the<br />

Project, on 26 th June 2008.<br />

Domestic Coal Linkage has also been sought<br />

from the Ministry of Coal, GOI.<br />

: Based on LTOA application, PGCIL has<br />

finalized the Transmission System, which was<br />

approved in the Southern Region Power<br />

Committee meeting held at Hyderabad on 27 th<br />

August 2009. Approval was also given to make<br />

LILO of Madurai, TNEB – NLC Joint Venture<br />

(JV) project 400 KV double circuit line and<br />

connect to the Energen’s Power Plant to draw<br />

start-up Power and Evacuate Power until the<br />

complete Transmission system is established.<br />

PGCIL has to give draft BPTA.<br />

Broad Status<br />

• Letter of Acceptance for Main Plant Order (EPC )<br />

issued to M/s BHELon 27.06.2008.<br />

• Advance released to BHEL on<br />

• 16.08.08 & on 30.03.09.<br />

• Letter of Intent ( LOI ) issued to BHEL<br />

• on 04.09.2008.<br />

• BOPs are common for both units.<br />

• Boiler ( M/s UB Engg. ) erection started on<br />

31.07.09.. Out of 25000 MT of boiler material, 5622<br />

MT has been erected upto 06/10.<br />

• Boiler drum lifted on 25/03/10.<br />

• Boiler pressure parts erection commenced.<br />

1070/10228 MT material erected.<br />

• Boiler hydraulic test expected by Nov’10.<br />

• ESP erection started on 10.08.09. Out of 8850 MT<br />

material,3113 MT erected up to 06/10.<br />

• Power house super structure erection is in progress.<br />

4842/8283 MT material fabricated and 2143 MT<br />

erected<br />

• STG deck: 100 % Staging work completed and<br />

80% concreting work completed.<br />

• 875 Acres of land is in possession for the project.<br />

• MOEF clearance received on 29.05.2008.<br />

• Civil Aviation clearance obtained on 16.05.08<br />

• PPA for 700 MW power signed with Tata Power<br />

Trading Company Ltd<br />

• PCB clearance obtained on 03.03.2009<br />

• BPTA signed with PGCIL on 24.02.2010.<br />

• CRZ clearance obtained on 10.08.09<br />

• Chimney: Work awarded to M/s Gammon India<br />

on 12.11.09. Raft foundation completed. Slip form<br />

erected.<br />

• CHP: Awarded to Thyssen Krupp Industries India<br />

on 18.03.10. Infrastructure works in progress.<br />

• AHP: bid evaluation is in progress.<br />

• CT: bid evaluation is in progress.<br />

• M/s Gammon India Ltd. has been awarded the<br />

BTG–Island civil & structural work on 12.11.09.<br />

Casting of foundation is in progress.<br />

• PT plant: Bid evaluation in progress.<br />

• DM Plant: Bid evaluation in progress.<br />

• CW system: Bids invited. Last date is 19.07.10<br />

• FO system: bid document is under finalization<br />

Unit-I<br />

• Blr. Erection to start in 12/10<br />

• Blr drum lifting expected in 2/11<br />

• TG erection to start in 12/10<br />

Unit-II<br />

• Blr. Erection to start in 10/10<br />

• Blr drum lifting expected in 04/11<br />

• TG erection to start in 02/11<br />

• Fire Prot system bid document under finalization<br />

• E-BOPs: Bid evaluation in progress.<br />

• M-BOPs: Bid document under finalization.<br />