Project Details<br />
North Chennai TPS<br />
St-II<br />
TNEB (Distt.<br />
Thiruvallur)<br />
U-2<br />
Capacity<br />
(MW)<br />
1200<br />
600 08/11<br />
10/11<br />
Date of Sanction : 25.06.2008<br />
Sanctioning <strong>Authority</strong> : Govt. of Tamil Nadu<br />
Org. Est. cost : Rs.271875 Lakh<br />
Commissioning Schedule<br />
Original Actual(A)/ As<br />
now Expected<br />
Syn. COD Syn. COD<br />
Comm<br />
Comm<br />
11/11 08/11<br />
11/11<br />
Latest Est. cost : -<br />
Expd.during 2008-2009 : Rs 21750 Lakh<br />
Expd.during 2009-2010 : Rs 42018 Lakh<br />
Expd.during 2010-2011<br />
(Up to 6/10)<br />
: Rs. 7045 Lakh<br />
Type of fuel : COAL<br />
Date of Main Plant<br />
Order<br />
: 16.08.2008 ( EPC ) on M/s BHEL<br />
Zero Date : 16.08.2008<br />
PRIVATE SECTOR<br />
Melamaruthur TPP<br />
(Coastal Energen)<br />
(Distt. Tuticorin) T.N.<br />
1200<br />
U-1 600 12/2011 12/2011<br />
Date of Sanction : 10.09.2007<br />
Date of financial closure : 02.07.2009<br />
U-2 600 03/2012 03/2012<br />
Org. Est. cost : Rs.480000 Lakh<br />
Latest Est. cost : Rs.480000 Lakh<br />
Expd. during 2007-2008 : Rs. 957 Lakh<br />
Expd. during 2008-2009 : Rs. 16689 Lakh<br />
Cumm.Expd. 2009-2010 : Rs. 50886 Lakh<br />
:<br />
Type of fuel : COAL<br />
Date of Main Plant<br />
Order<br />
Zero Date<br />
Fuel Linkage<br />
Associated Transmission<br />
System<br />
- 99 -<br />
01/12<br />
: 25.02.2009 ( BTG) on M/s Harbin -<br />
- Power Engg. Co. Ltd. China.<br />
: 06.08.2009<br />
: The Company has entered into Fuel Supply<br />
Agreement (FSA) with M/s Coal & Oil, Dubai<br />
for Supply of Entire Coal requirement for the<br />
Project, on 26 th June 2008.<br />
Domestic Coal Linkage has also been sought<br />
from the Ministry of Coal, GOI.<br />
: Based on LTOA application, PGCIL has<br />
finalized the Transmission System, which was<br />
approved in the Southern Region Power<br />
Committee meeting held at Hyderabad on 27 th<br />
August 2009. Approval was also given to make<br />
LILO of Madurai, TNEB – NLC Joint Venture<br />
(JV) project 400 KV double circuit line and<br />
connect to the Energen’s Power Plant to draw<br />
start-up Power and Evacuate Power until the<br />
complete Transmission system is established.<br />
PGCIL has to give draft BPTA.<br />
Broad Status<br />
• Letter of Acceptance for Main Plant Order (EPC )<br />
issued to M/s BHELon 27.06.2008.<br />
• Advance released to BHEL on<br />
• 16.08.08 & on 30.03.09.<br />
• Letter of Intent ( LOI ) issued to BHEL<br />
• on 04.09.2008.<br />
• BOPs are common for both units.<br />
• Boiler ( M/s UB Engg. ) erection started on<br />
31.07.09.. Out of 25000 MT of boiler material, 5622<br />
MT has been erected upto 06/10.<br />
• Boiler drum lifted on 25/03/10.<br />
• Boiler pressure parts erection commenced.<br />
1070/10228 MT material erected.<br />
• Boiler hydraulic test expected by Nov’10.<br />
• ESP erection started on 10.08.09. Out of 8850 MT<br />
material,3113 MT erected up to 06/10.<br />
• Power house super structure erection is in progress.<br />
4842/8283 MT material fabricated and 2143 MT<br />
erected<br />
• STG deck: 100 % Staging work completed and<br />
80% concreting work completed.<br />
• 875 Acres of land is in possession for the project.<br />
• MOEF clearance received on 29.05.2008.<br />
• Civil Aviation clearance obtained on 16.05.08<br />
• PPA for 700 MW power signed with Tata Power<br />
Trading Company Ltd<br />
• PCB clearance obtained on 03.03.2009<br />
• BPTA signed with PGCIL on 24.02.2010.<br />
• CRZ clearance obtained on 10.08.09<br />
• Chimney: Work awarded to M/s Gammon India<br />
on 12.11.09. Raft foundation completed. Slip form<br />
erected.<br />
• CHP: Awarded to Thyssen Krupp Industries India<br />
on 18.03.10. Infrastructure works in progress.<br />
• AHP: bid evaluation is in progress.<br />
• CT: bid evaluation is in progress.<br />
• M/s Gammon India Ltd. has been awarded the<br />
BTG–Island civil & structural work on 12.11.09.<br />
Casting of foundation is in progress.<br />
• PT plant: Bid evaluation in progress.<br />
• DM Plant: Bid evaluation in progress.<br />
• CW system: Bids invited. Last date is 19.07.10<br />
• FO system: bid document is under finalization<br />
Unit-I<br />
• Blr. Erection to start in 12/10<br />
• Blr drum lifting expected in 2/11<br />
• TG erection to start in 12/10<br />
Unit-II<br />
• Blr. Erection to start in 10/10<br />
• Blr drum lifting expected in 04/11<br />
• TG erection to start in 02/11<br />
• Fire Prot system bid document under finalization<br />
• E-BOPs: Bid evaluation in progress.<br />
• M-BOPs: Bid document under finalization.<br />
Critical<br />
Areas