Sl.<br />

No.<br />

Project Details<br />

Capacity<br />

(MW)<br />

Commissioning Schedule<br />

Original Actual(A) / As<br />

now Expected<br />

Syn. COD Syn. COD<br />

(Com.) (Com.)<br />

B. PROJECT UNDER CONSTRUCTION<br />

PRIVATE SECTOR<br />

1. Jhajjar TPP<br />

CLP Power India Ltd.<br />

(Distt-Hissar)<br />

1320<br />

U-1 660 11/11 01/12 11/11 01/12<br />

(12/11) (12/11)<br />

U-2 660 03/12 07/12 03/12 05/12<br />

Date of Sanction /<br />

Investment Decision<br />

(04/12)<br />

(04/12)<br />

Sanctioning <strong>Authority</strong> Govt. of Haryana<br />

Est.approved cost Rs.600000 Lakhs<br />

Expenditure (upto 3/08) Nil<br />

Cum. Expenditure (upto 1/09) Rs. --- lakhs<br />

Type of fuel Coal<br />

Fuel Linkage A long term coal linkage has been<br />

awarded by the standing committee<br />

(SC(LT)) under Ministry of Coal, Govt.<br />

of India.<br />

Order main plant<br />

Power Evacuation system<br />

M/s SEPCOIII, China.<br />

- 40 -<br />

Broad Status<br />

a) M/s SEPCOIII, China is Main plant<br />

suppler.<br />

b) MOE&F clearance obtained on 24.4.08.<br />

c) Boiler will be sourced from Harbin<br />

boiler co Ltd.<br />

d) Turbine & Auxiliaries will be sourced<br />

from Dongfang Turbine Corporation<br />

Limited, China.<br />

e) Generator will be sourced from<br />

Dongfang Electric Machinery co Ltd.,<br />

China.<br />

f) Foundation construction for chimney is<br />

in progress.<br />

g) NDCT diagonal column 80% completed.<br />

h) Excavation for coal handling plant and<br />

wagon tippler is in progress.<br />

i) Casting of racker column of cooling<br />

tower #1 started.<br />

Unit-1<br />

a. Foundation work for main power house<br />

and boiler area for Unit-1 completed.<br />

b. Coal bunker erection is in progress.<br />

c. 6 out of 7 layers of boiler erection<br />

completed.<br />

d. ESP structural erection work is in<br />

progress.<br />

Unit-2<br />

a. Structural steel erection is in progress.<br />

Column erection of 3 rd row is in<br />

progress.<br />

Critical<br />

Areas