Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Sl.<br />
No.<br />
Project Details<br />
Commissioning Schedule<br />
Capacity<br />
(MW)<br />
Original Actual(A) / As<br />
now Expected<br />
Syn. COD Syn. COD<br />
(Com.) (Com.)<br />
C. PROJECTS WHERE CONTRUCTION IS YET TO START<br />
1.<br />
PRIVATE SECTOR<br />
Goindwal Sahib TPP<br />
M/s GVK Power<br />
(Goindwal Sahib) Ltd.<br />
540<br />
(Distt. TaranTaran)<br />
Unit-1<br />
Unit-2<br />
270<br />
270<br />
3/09 36/42 months from 3/09<br />
11/0 Financial Closure<br />
11/09<br />
Date of clearance by state Govt. State Cleared<br />
Est. approved cost (revised)<br />
Revised cost after approval of<br />
Appellate Tribunal order dated<br />
08.04.09<br />
Rs. 298786 Lakhs<br />
Rs.296381 Lakhs<br />
Exp. upto 11/2008 Rs. 29207 Lakhs<br />
Financial closure : 12 months from PPA approval<br />
by PSERC(Exptd by May’10)<br />
Type of fuel Coal<br />
Fuel linkage From SEREGARHA coal block<br />
in Jharkhand<br />
Date of main plant order : Aug’08 on M/s BHEL<br />
Power Evacuation Facility to be completed by<br />
PSEB<br />
7 months prior to COD.<br />
- 42 -<br />
Broad Status<br />
a) PPA was signed on 17.04.2000. Restated<br />
PPA initialed on 06.02.07.<br />
b) NOC from MOE&F was obtained on<br />
23.09.99 for 2x281 MW. Revised NOC from<br />
MOE&F obtained on 09 th May’08 for 2x300<br />
MW.<br />
c) Capacity further revised by the firm from<br />
300 MW to 270 MW.<br />
d) Out of the total land 1014 acres required for<br />
the project M/s GVK is in possession of 53<br />
acres, balance land acquisition is under<br />
progress as per the approval of PSERC and<br />
Govt.of Punjab.<br />
e) LOI issued on 18.5.98 by Govt. of Punjab<br />
has expired, IDBI have indicated that they<br />
will consider revalidation of LOI only after<br />
significant progress has been made by Govt.<br />
of Punjab/PSEB to establish Escrow capacity<br />
of PSEB to support the project.<br />
f) Orders for BTG package placed on M/s<br />
BHEL and for BOP package on M/s Punj<br />
Lloyd Ltd.<br />
g) Financial closure is expected to achieve by<br />
May’10.<br />
h) Civil works of leveling & grading has<br />
commenced.<br />
i) Engineering work in progress for both BTG<br />
package & BOP packages<br />
j) Leveling of land and construction of<br />
boundary wall commenced on 09.06.09<br />
k) Foundation for start of construction activity<br />
laid on 18.10.08.<br />
l) Coal requirement will be met from captive<br />
coal mine in Tokisud North sub block in<br />
Jharkhand. In order to supplement coal<br />
supply to Goindwal Sahib TPP GOI, Min. of<br />
Coal has allotted SEREGARHA coal block<br />
in Jharkhand vide lr.no. 38011/1/2007-CA-1<br />
of 09.01.08. The SEREGARHA coal block<br />
has to be jointly developed by GVK and M/s<br />
ARCELLOR MITTAL.<br />
m) GVK signed coal transport agreement with<br />
Indian railways on 11.12.08.<br />
Final MOU has been signed between M/s<br />
GVK and PSEB on 8.2.2006 for execution of<br />
the project. The validity of MOU has been<br />
extended upto 02.08.09. The amended and<br />
restated PPA signed on 26.05.09 by both<br />
GVK & PSEB after the Appellate<br />
Tribunal permitting on 19.05.09 for<br />
signing the PPA. However, the appeal was<br />
listed for hearing on 18.05.2010<br />
Critical<br />
Areas<br />
i.<br />
Approval<br />
of redrafted<br />
PPA by<br />
PSERC.<br />
ii.<br />
Achieving<br />
of<br />
financial<br />
closure.