Sl.<br />

No.<br />

Project Details<br />

Capacity<br />

(MW)<br />

II PROJECTS UNDER CONSTRUCTION<br />

9 Farakka STPS Stage-III<br />

(Distt Murshidabad, WB) 500<br />

Unit-6<br />

Investment Approval<br />

Sanctioning <strong>Authority</strong><br />

Estimated cost<br />

Exp.during 2005-06<br />

2006-07<br />

2007-08<br />

2008-09<br />

Expenditure (up to 03/10)<br />

Budget Estimate 10-11<br />

Exp. During 10-11<br />

(up to 04/10)<br />

Type of Fuel<br />

Date of Main Plant Order<br />

10 Barh STPP<br />

(Mega Power Project<br />

(Distt.Patna, Bihar)<br />

Unit-1<br />

Unit-2<br />

Unit-3<br />

Date of TEC<br />

Investment Approval<br />

Est. approved cost<br />

(Completed cost)<br />

Latest approved cost.<br />

Exp.during 2005-06<br />

2006-07<br />

2007-08<br />

2008-09<br />

Exp. upto 03/10<br />

Budget Estimate (10-11)<br />

Exp. During 10-11<br />

(up to 04/10)<br />

Type of Fuel<br />

Date of Main Plant Order<br />

500<br />

Commissioning Schedule<br />

Original Actual (A) /As<br />

Syn.<br />

comm<br />

08/10<br />

12/10<br />

: 31.07.2006<br />

: NTPC Board<br />

: Rs 257044 Lakhs<br />

: Rs. 0.0 lakhs<br />

: Rs.14464 lakhs<br />

: Rs.42695 lakhs<br />

: Rs.61675 lakhs<br />

: Rs 171900 Lakhs<br />

: Rs 52700 Lakhs<br />

: Rs 900 Lakhs<br />

now expected<br />

COD Syn.<br />

comm<br />

COD<br />

01/11<br />

: Coal<br />

: 30/10/2006 on M/S BHEL<br />

1980<br />

12/10<br />

02/11<br />

660 03/09 04/13<br />

08/09 07/13<br />

660 01/10 10/13<br />

06/10 01/14<br />

660 11/10 04/14*<br />

04/11 07/14<br />

: 28.9.2001<br />

: 21. 02.2005<br />

: US $ 1070.387 Mn + Rs.411563.2<br />

lakhs<br />

(Exchange rate 1 US$ = Rs.46.50)<br />

= Rs. 909293 lakhs<br />

: Rs 869297 lakhs<br />

: Rs.19575 lakhs<br />

:Rs.54738 lakhs<br />

:Rs.130360 lakhs<br />

:Rs.132139 lakhs<br />

: Rs.466200 lakhs<br />

: Rs. 73200 lakhs.<br />

: Rs 1800 lakhs<br />

: Coal<br />

: SG: 14/03/2005 on M/S<br />

Technopromexport Russia<br />

:TG: 14/03/2005 on M/S<br />

Powermachines, Russia.<br />

03/11<br />

* Based on SG erection start by 10//10 for<br />

Unit-1<br />

- 22 -<br />

Broad Status<br />

a. Environmental clearance accorded on<br />

07/02/2007. MOEF clearance obtained<br />

in 02/2007.<br />

b. Boiler erection started on 30/09/2007.<br />

Boiler drum lifting completed on<br />

04.02.09. Hydraulic test completed in<br />

03/10. BLU expected in 08/10.<br />

c. TG erection started in 02/09. TG box<br />

up completed on 27.02.10.<br />

d. Order for DM Plant placed on M/s<br />

Driplex.<br />

e. AHP: Civil works in progress.<br />

f. Chimney: Shell casting completed. Flue<br />

can erection is in progress.<br />

g. CT: civil works completed.<br />

a) An approx. 1300 acre of land is under<br />

legal possession. Approximately 1372<br />

acres of land has been physically<br />

acquired. Land filling and leveling is<br />

under progress at site.<br />

b) MOE&F clearance has been received<br />

on 03/08/2004<br />

c) Coal linkage is available. However<br />

FSA is under negotiations with<br />

CCL/CIL.<br />

d) Cooling Tower.: Excavation and<br />

concreting are in progress.<br />

e) Chimney. RCC shell concreting of<br />

chimney’s completed. Flue can<br />

erection is in progress.<br />

f) Coal Handling Plant: Excavation,<br />

concreting and erection are in progress.<br />

g) Off site Area Civil Works<br />

Concreting is in progress.<br />

h) Ash Dyke : Stripping, excavation,<br />

earth and embankment filling are in<br />

progress.<br />

Unit-1<br />

a) Boiler erection agency is yet to be<br />

finalized. Condenser parts supplied. TG<br />

deck concreting stage-I completed.<br />

Unit-2<br />

a) Boiler erection expected to start in<br />

10/2010.<br />

b) TG raft completed. Columns up to 12.2<br />

m completed. TG deck concreting state-<br />

I completed. Condenser material<br />

received at site.<br />

Unit – 3<br />

a) Boiler erection started in 1/08 by M/s<br />

NTPC.<br />

b) TG deck concreting state-I completed.<br />

Critical<br />

Areas<br />

Slow pace<br />

of boiler<br />

erection<br />

works by<br />

BHEL.<br />

supply of<br />

balance<br />

NMEJs ,<br />

fuel oil<br />

material,<br />

Balance<br />

Ducting<br />

and P-91<br />

joints<br />

Delay in<br />

Finalization<br />

of boiler<br />

erection<br />

Agency<br />

as TPE<br />

wants<br />

removal<br />

of ceiling<br />

on price<br />

variation<br />

s. MOP<br />

directed<br />

NTPC to<br />

carry on<br />

with the<br />

contract<br />

with<br />

TPE.<br />

Board of<br />

Directors<br />

of NTPC<br />

approved<br />

the<br />

proposal<br />

to go<br />

ahead<br />

with the<br />

contract<br />

with<br />

TPE.<br />

Delay in<br />

Supply of<br />

TG<br />

Embedmen<br />

t by Power<br />

Machines<br />

by M/s<br />

Power<br />

Machine,<br />

Russia.