Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Sl.<br />
No.<br />
6<br />
7.<br />
PROJECT DETAILS<br />
Lanco Amarkantak Mega<br />
TPS ( Pathadi )<br />
(Distt. Korba )<br />
M/s LAP Pvt. Ltd.<br />
Phase-II<br />
Capacity<br />
(MW)<br />
1200<br />
Commissioning Schedule<br />
Original Actual(A) / As<br />
now Expected<br />
Syn. Comm Syn. Comm<br />
Unit-3 600 01/12 01/12 01/12 01/12<br />
Unit-4 600<br />
Date of TEC : Not Required<br />
Date of Appr. State Govt. :<br />
Est. approved cost<br />
Unit-3 Unit-4<br />
: Rs.344285 Lakhs Rs. 344315 Lakhs<br />
Exp. During 2008-09 : Rs. 384 lakhs<br />
Exp. During 2009-10 : Rs.11323 lakhs<br />
Exp. During 2010-11 : Rs 1261 lakhs<br />
( up to 05/10)<br />
Cum.Exp. up to 05/10 : Rs. 12968 lakhs<br />
Financial Closure : Unit-3<br />
: Unit-4<br />
Zero date : Unit-3: 17.11.09<br />
: Unit-4:<br />
Type of fuel : COAL<br />
Date of Main Plant Order Unit-3 &4: Main plant package (BTG)<br />
awarded on 17.11.09 to M/s DEC<br />
Power evacuation System LTOA approved and BPTA signed. Pooling<br />
station location at Champa to be confirmed by<br />
Singhitarai TPP<br />
( DumatpalliTPP)<br />
Janjgir (Vill)<br />
Champa Distt.<br />
(M/s Athena Chhattisgarh<br />
Power Ltd)<br />
PGCIL to start survey.<br />
1200<br />
Unit-1 600 03/12<br />
Unit-2 600<br />
Date of TEC : Not Required<br />
Date of Appr. State Govt. :<br />
Unit-1 Unit-2<br />
Est. approved cost<br />
Exp. During 2008-09<br />
Exp. During 2009-10<br />
Cum.Exp. up to 03/10<br />
Financial Closure<br />
Zero date<br />
Type of fuel : COAL<br />
Date of Main Plant Order<br />
Power evacuation System<br />
Unit-1 &2 : Main plant package (BTG)<br />
awarded on 21.12.09 to M/s DEC<br />
- 58 -<br />
Broad Status<br />
1) Main plant package (BTG) awarded<br />
on 17.11.09 on M/s DEC as vendor and<br />
award of contracting agency on 12.11.09<br />
on M/s HTC/HEC .<br />
2) PPA Consent letter received from<br />
CSPTCL on 07.10.09 for purchase of<br />
35% as per implementation agreement.<br />
3) FSA: For unit-3 – LOA issued by<br />
SECL on 06.06.09. For Unit-4- SLC<br />
(LT) meeting on 29.01.10 cleared and<br />
notice received from SECL for payment<br />
of commitment charges with in 30 days<br />
received on 30.04.10.<br />
4) Additional land acquisition is in<br />
progress.<br />
5) Sanction of Water requirement for U-<br />
3 & U-4 received from Govt. of<br />
Chhattisgarh.<br />
6) MOEF clearance for unit-3 received<br />
on 04.09.08 and for Unit-4 pending in<br />
MOEF.<br />
7) NOC for 275 m . Twin flue chimney<br />
was obtained on 25.08.08 from AAI.<br />
Unit-3:<br />
Detailed engineering review is under<br />
progress. Some BOPs awarded and<br />
others are in process for awarding.<br />
1)Main plant package (BTG) awarded<br />
on 21.12.09 on M/s DEC .<br />
2) State pollution control board clearance<br />
yet to be received. Due to SPCB approval<br />
, all the activities are pending.<br />
Critical<br />
Areas<br />
MOEF<br />
clearance for<br />
unit-4 is long<br />
pending<br />
issue.<br />
2)<br />
SPCB<br />
clearance 4 is<br />
long pending<br />
issue.