BROAD STATUS OF THERMAL POWER PROJECTS IN PUNJAB<br />
Capacity<br />
(MW)<br />
Commissioning Schedule<br />
Original Actual(A) / As<br />
now Expected<br />
Syn. COD Syn. COD<br />
(Com.)<br />
(Com.)<br />
A. PROJECT COMMISSIONED –Nil-<br />
B. PROJECT UNDER CONSTRUCTION<br />
STATE SECTOR<br />
1. GHTP ST.II<br />
(Lehra Mohabbat)<br />
PSEB<br />
(Distt. Bathinda)<br />
500<br />
Unit-3* 250 10/06 12/06 01/08(A)<br />
11/06 02/08(A)<br />
Unit-4* 250 01/07 03/07 07/08(A)<br />
02/07<br />
02/08(A)<br />
Date of TEC 15.09.2000<br />
Date of Sanction 20.03.2001<br />
Sanctioning <strong>Authority</strong> Planning Commission.<br />
Est. approved cost Rs.178967 lakhs<br />
Latest Est. Cost Rs.233900 lakhs<br />
- 41 -<br />
10/08(A)<br />
Cumm. Exp. upto 03/2008 Rs. 193221 lakhs<br />
Exp.During 2008-09 (Upto 9/08) Rs. 29251 lakhs<br />
Type of fuel Coal<br />
Fuel Linkage Pachhwara captive coal block<br />
Date of main plant order<br />
* Slipped from 10<br />
31.03.2004 on M/s BHEL (EPC)<br />
th Plan<br />
06/09<br />
Broad Status<br />
a) M/s TCE are the consultants for the<br />
Project.<br />
b) Coal handling plant: Order has been<br />
placed on M/s Elecon, Gujarat.<br />
Unit-3<br />
a) Unit synchronised on 3 rd<br />
Jan’2008.Coal firing is done on<br />
05.02.08.<br />
b) Unit achieved full load on 27 th<br />
Feb’08.<br />
c) Trial run successfully completed on<br />
16.10.08.<br />
Unit-4<br />
a) Unit synchronised on 31 st Jul’2008.<br />
Coal firing completed on 2 nd Aug’08.<br />
Unit achieved full load on 1 st Feb’09.<br />
Critical<br />
Areas