Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Sl.<br />
No.<br />
2<br />
Project Details<br />
Tuticorin TPP<br />
TN joint venture with<br />
NLC ( NTPL )<br />
Distt. Tuticorin, TN.<br />
U-1<br />
U-2<br />
Capacity<br />
(MW)<br />
1000<br />
500<br />
500<br />
Commissioning Schedule<br />
Original Actual(A)/ As<br />
now Expected<br />
Syn. COD Syn. COD<br />
01/12<br />
03/12<br />
06/12<br />
08/12<br />
Date of Sanction : 12.05.2008.<br />
Sanctioning <strong>Authority</strong> CCEA<br />
Date of Inv. Approval. 12.05.2008.<br />
Est. cost Rs 490954 Lakh<br />
Latest Est. Cost Rs 490954 Lakh<br />
Exp. during 2007-2008 Rs 827 Lakh<br />
Exp.during 2008-2009 Rs 22042 Lakh<br />
Exp. during 2009-10 Rs 50146 Lakh<br />
Exp. during 2010-11<br />
( upto 04/2010)<br />
Rs 15750 Lakh<br />
Type of fuel<br />
Date of Main Plant<br />
Order<br />
: COAL<br />
Zero Date<br />
: 28.01.2009.<br />
Fuel Linkage<br />
04/12<br />
09/12<br />
01/12<br />
03/12<br />
06/12<br />
08/12<br />
: 28.01.2009 ( BTG) on M/s BHEL.<br />
: Long term coal linkage for 4.624<br />
MTPA of coal is available from<br />
Talcher coal fields.<br />
- 28 -<br />
04/12<br />
09/12<br />
Broad Status<br />
• 108 hectares of Land is available.<br />
• Sea water after treatment.<br />
• MOE&F clearance accorded on<br />
13.06.2007.<br />
• M/s MECON appointed consultant<br />
for the project .<br />
• Funding is arranged with RECL.<br />
• PPA signed with TNEB, ESCOMs<br />
of Karnataka, PED Puducherry and<br />
KSEB.<br />
• CHP order placed on 31.07.09 (M/S<br />
L&T). Piling works started in<br />
Dec’09. 1561 piles completed by<br />
6/10<br />
• AHP order placed 08.04.10 (Energo)<br />
• CW pumps order placed on 31.10.09<br />
(M/s KBL)<br />
• CT order placed on 12.03.10 (M/s<br />
Gammon). Soil investigation I/p<br />
• CW system: Soil investigation is<br />
conducted.<br />
• Order for AHP placed on 08.04.10<br />
(M/s Energo)<br />
• Chimney Order placed on 29.01.10<br />
(M/s Gamon). Soil investigation<br />
completed.<br />
• Order for Boiler placed on 28.01.09<br />
(M/s BHEL). Excavation for boiler<br />
foundations commenced on 06.01.10<br />
• Piling work in ESP area commenced<br />
in 01/10. 1247 piles completed by<br />
6/10<br />
• Order for Switchyard placed on<br />
29.01.10 (M/s L&T).<br />
Critical<br />
Areas