SUMMARY OF MAJOR BOPs OF THERMAL PROJECTS WHICH ARE UNDER CONSTRUCTION AND<br />
LIKELY TO BE COMMISSIONED DURING 11th PLANS .<br />
( INCLUDING ADDITIONAL AND BEST EFFORTS PROJECTS)<br />
Sl.NO Name of BOP BOPs<br />
required for<br />
Projects<br />
Under<br />
Construction<br />
12<br />
Order<br />
already<br />
Placed<br />
AS ON 22.06.10<br />
Balance order to<br />
be Placed<br />
1 Coal Handling Plant ( CHP) 51 49 2<br />
2 Ash Handling Plant ( AHP) 52 50 2<br />
3 Demineralized Water Plant (DM) 52 48 4<br />
4 Cooling Tower 99 97 2<br />
5 Chimney/ Stack 75 74 1<br />
6 Fuel Oil System( FO) 52 49 3<br />
7 PT Plant 55 51 4<br />
Total 436 418 18<br />
* - CCGTs (not required CHP & AHP)