BROAD STATUS OF THERMAL POWER PROJECTS IN HARYANA<br />
Commissioning Schedule<br />
Sl.<br />
No.<br />
Project Details Capacity<br />
(MW)<br />
Original Actual(A) / As<br />
now Expected<br />
Broad Status<br />
Critical<br />
Areas<br />
Syn. COD Syn. COD<br />
(Com.)<br />
PROJECTS INCLUDED IN 11<br />
(Com.)<br />
TH PLAN<br />
A. PROJECT COMMISSIONED<br />
1. DCR TPP,<br />
600<br />
Provisional taking over of the Project is<br />
Yamunanagar HPGCL<br />
Distt. Yamuna nagar<br />
affected from 31.08.2009.<br />
Unit-1<br />
Unit-2<br />
Sanctioning <strong>Authority</strong><br />
Est.approved cost<br />
Expenditure till 3/08<br />
Cumm. Exp. Upto 9/08<br />
Type of fuel<br />
Fuel Linkage<br />
Date of Turn key contract<br />
300 10/07 11/07 11/07(A) 04/08(A) Unit-1<br />
11/07 02/08(A)<br />
Unit synchronised on 13<br />
300 01/08 02/08 03/08(A) 06/08 (A)<br />
02/08 05/08(A)<br />
Govt. of Haryana<br />
Rs. 240097 lakhs<br />
Rs. 219951 lakhs<br />
Rs. 8833 lakhs<br />
Coal<br />
29.09.04 on Reliance Energy Ltd. At a<br />
cost of Rs.2097 Crs.<br />
Order for Main Plant 20.8.05 on M/s Shanghai Electric Corp.,<br />
China.<br />
th Nov’07. Coal<br />
firing achieved on 11 th Jan’08. Full load<br />
achieved on 3 rd Feb’08.Trial run completed<br />
on 14.04.2008 and declared on COD w.e.f<br />
14 th April’ 08.<br />
Unit-2<br />
Unit synchronised on 29 th Mar’08. Coal<br />
firing achieved on 10.04.08, full load<br />
achieved. Trial operation commenced on<br />
10.6.08 and 72 Hrs full load operation<br />
achieved on 13.6.08. Trial run completed<br />
on 24.06.2008.<br />
B. PROJECT UNDER CONSTRUCTION<br />
STATE SECTOR<br />
1. Rajiv Gandhi TPP 1200<br />
a) LOI Placed on M/s Reliance Energy<br />
HPGCL,<br />
Limited on EPC basis on 29.01.2007.<br />
(Distt-Hisar)<br />
b) Order for BTG package has been<br />
U-1 600 11/09 12/09 12/09(A) 07/10<br />
12/09 4/10(A)<br />
U-2 600 02/10 03/10 04/10(A) 09/10<br />
03/10<br />
07/10<br />
Date of Sanction / Investment Decision<br />
Sanctioning <strong>Authority</strong> Govt. of Haryana<br />
Est.approved cost Rs.433738 Lakhs<br />
Exp. during 2006-07 Rs. 19000 lakhs<br />
Exp. during 2007-08 Rs. 46995 lakhs<br />
Exp. during 2008-09 Rs. 179272 lakhs<br />
Exp. during 2009-10 Rs. 125606 lakhs<br />
Exp. during 2010-11 Rs. -- lakhs<br />
Type of fuel Coal<br />
Fuel Linkage 5.55MTPA From Mahanadi coalfields<br />
placed on M/s Shanghai & Electric.<br />
Co in Feb’07.<br />
Unit-1:<br />
a) Boiler drum lifted on 10.9.08. Boiler<br />
Hydro test completed on 28.2.09.<br />
b) Turbine erection started on 24.11.08.<br />
c) Condenser erection started on<br />
28.11.08. TG Unit boxed up on<br />
15.09.09.<br />
d) Boiler light up achieved on 22<br />
Ltd.<br />
Order main plant EPC contract on M/s REL on 29.1.07<br />
BTG Package on M/s Shanghai Electric.<br />
Co in Feb’07.<br />
Power Evacuation System 400 KV D/C Fatehabad-RGTPP line &<br />
400 KV D/C Kirori-RGTPP line.<br />
400 KV LILO Hisar-Monga for start-up.<br />
nd<br />
Aug’09. Unit Synchronized on<br />
29.12.2009.<br />
e) Unit Commissioned on 1.4.10.<br />
Unit-2:<br />
Boiler<br />
a) Boiler erection commenced on 31st<br />
Dec’07. Boiler drum lifted on 6.11.08.<br />
b) Boiler Hydro test completed on<br />
17.4.09.<br />
c) Boiler light up completed on 27 th<br />
Jan’2010.<br />
TG<br />
a) Condenser erection completed.<br />
b) HP, IP & LP turbine box-up completed<br />
on 2 nd Feb’ 2010.<br />
c) Unit is synchronized on 24 th .<br />
April’<br />
2010.<br />
d) Unit expected to be commissioned in<br />
July’10.<br />
- 39 -