Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Sl.<br />
No.<br />
3.<br />
Project Details<br />
Capacity<br />
(MW)<br />
Commissioning Schedule<br />
Original Actual (A) / As<br />
Syn.<br />
(Com.)<br />
now Expected<br />
COD Syn.<br />
(Com.)<br />
COD<br />
Anpara ‘C’TPS<br />
UPRVUNL/<br />
Lanco Anpara Power<br />
Ltd.<br />
(Dist: Sonebhadra)<br />
1200<br />
Unit-1<br />
600 11/10 03/11 11/10<br />
(02/11) (01/11)<br />
Unit-2<br />
600 03/11 07/11 03/11<br />
(06/11) (05/11)<br />
Date of TEC Not Required<br />
Date of approval by State Govt. NA<br />
03/1<br />
1<br />
07/1<br />
1<br />
Est. approved cost Rs. 411480 lakhs<br />
Latest Est. Cost Rs. 411480 lakhs<br />
Exp Upto 31.03.2008 Rs. 48900 lakhs.<br />
Exp Upto 31.03.2009 Rs. 84700 lakhs<br />
Exp Upto 31.03.2010 Rs. 162700 lakhs<br />
Total Exp. Upto 31.03.2010 Rs. 296300 lakhs<br />
Total Exp. May, 2010 Rs. 313400 lakhs<br />
Financial Closure Achieved on 24th Nov’07 with<br />
REC.<br />
Type of fuel Coal<br />
Coal Linkage Yet to be finalized with CIL/NCL<br />
Date of main plant order EPC contract on M/s Lanco<br />
Infratech Ltd.(LIL) on<br />
15.11.07.<br />
BTG supply package contract<br />
placed on M/s Dongfang Electric<br />
Co., China in Nov’07.<br />
Zero date 23 rd Nov’07.<br />
Power Evacuation system 400KV & 765 KV Transmission<br />
system<br />
- 52 -<br />
Broad Status<br />
a) Letter of acceptance placed on M/s<br />
Lanco Anpara Power Pvt .Ltd. by<br />
UPRVUNL on 27.09.2006 for<br />
2x500 MW.<br />
b) The project has achieved financial<br />
closure on 24 th Nov’07 with REC.<br />
c) MOE&F clearance obtained on 26.11.07.<br />
d) EPC contract for 2x600 MW was<br />
awarded on 15 th Nov’07 to M/s Lanco<br />
Infratech Ltd.(LIL).<br />
e) Switchyard: Consultancy contracts<br />
awarded on RITES for civil works of<br />
Switchyard and MGR system.<br />
Equipment.<br />
f) 400 kV Switchyard equipment erection<br />
completed. 765 kV Switchyard<br />
foundation & structure & equipment<br />
erection in progress.<br />
g) Chimney: RCC shell casting completed<br />
& Flue can fabrication under progress.<br />
h) CHP: Track hopper RCC work is in<br />
progress. TP# 1& 2 & Crusher house<br />
Structure fabrication & erection is in<br />
progress.<br />
i) MGR civil works under progress<br />
j) AHP: AW and Ash slurry pump house,<br />
RCC work is in progress.<br />
k) ID Cooling Tower: Mechanical rection in<br />
progress.<br />
l) CW Pump house: RCC & CW duct<br />
erection work is in progress.<br />
m) DM plan- 1 st stream commissioned in<br />
04/10<br />
Unit-1<br />
a) Boiler erection started on 20 th Dec.08.<br />
b) Boiler drum lifing completed on<br />
18.08.09.<br />
c) HT completed on 27.03.10<br />
d) Condenser erection started on 30.09.09.<br />
e) TG: Erection started on 15.12.09.<br />
f) Generator Stator placed in position.<br />
Unit-2<br />
a) Boiler erection started on 25.2.09.<br />
b) 5 th tier erection is in progress.<br />
c) Structural steel fabrication started and<br />
150MT is under dispatch.<br />
d) Boiler drum lifting completed on 23 rd<br />
September, 09<br />
e) Condenser erection commenced 28.04.10<br />
TG erection commenced on 27.04.10<br />
Critical<br />
Areas<br />
• Completion<br />
of 765 kV<br />
switchyard<br />
at Unnao<br />
by UPPCL