BROAD STATUS OF THERMAL POWER PROJECTS IN ANDRA PRADESH<br />

Commissioning Schedule<br />

Sl.<br />

Cap. Orig. Act.(A)/As Now exp.<br />

No. Project Details (MW) Syn. COD Syn. COD<br />

Broad Status<br />

Com<br />

Com<br />

A. PROJECTS INCLUDED IN 11TH PLAN<br />

I. PROJECTS COMMISSISONED<br />

STATE SECTOR<br />

1. Rayalaseema TPP<br />

U-3: Synchronised on 25.1.2007.Coal<br />

St-II<br />

420<br />

firing was carried out on 01.03.07.Full<br />

(M/s APGENCO)<br />

load was achieved on 29.5.07.Unit<br />

Distt. Cuddapah<br />

declared commercial w.e.f. 15.08.2007.<br />

Unit-3<br />

210 09//06 01/07(A) 08/07(A) U-4: Unit synchronized on 20.11.2007.<br />

12/06<br />

05/07(A)<br />

Coal firing also achieved on 20.11.2007.<br />

Unit-4<br />

210 12/06<br />

11/07(A) 03/08(A) Full load achieved on 30.1.08. Unit<br />

03/07<br />

01/08(A)<br />

declared commercial w.e.f. 29.03.2008.<br />

TEC Date (Revised) : 03/2001<br />

Est. Org. cost : Rs.164000 lakhs<br />

Latest Est. cost : Rs.164000 lakhs<br />

Expenditure pto3/07: Rs 148000 lakhs<br />

During 2007-08 : Rs. 21200 lakhs ( upto 12/2007)<br />

Financial Closure : Achieved on 30.4.04.<br />

Type of Fuel : Coal<br />

Order Date : Placed on BHEL on 27.12.2003.<br />

2. Dr NT Rao TPS 500<br />

• Boiler erection commenced on<br />

ST-IV<br />

18.08.06 .<br />

(Vijayawada)<br />

• Boiler drum lifted on 10.05.07.<br />

(M/s APGENCO)<br />

08/08 12/08 04/09(A) 01/10(A)<br />

Distt. Krishna 500 11/08<br />

10/09 (A)<br />

Unit-1<br />

Date of TEC : 28.02.2003<br />

Org. Est. Cost : 210029.9 Lakhs<br />

Lat. Est. Cost : 221457 Lakhs<br />

Expediture upto3/07 Rs. 51146 lakhs<br />

During 2007-08 : Rs. 73440 lakhs<br />

During 2008-09 Rs. 25200 lakhs<br />

During 2009-10 : Rs. 18214 lakhs (Upto 12/09)<br />

Zero Date: 05.08.05<br />

Financial closure : Achieved<br />

Fuel (Coal) Linkage : SLC (LT)-3.50 million tons per annum from MCL.<br />

Power Evacuation : 400 kV D/C line for LILO from Numma – Srisailam<br />

400 kV D/C line to VTPS (stage-IV) (Double Circuit LILO)<br />

VTPS (Stage-IV)-Malkaram 400 kV line .<br />

• Boiler Hyd.Test completed on<br />

28.12.07.<br />

• Boiler light up completed on 25.12.08.<br />

• SBO started on 20.02.09 and<br />

completed on 05.03.09.<br />

• TG erection started on 29.10.07.<br />

• TG boxed up on 28.03.09.<br />

• Oil flushing completed.<br />

• TG put on Barring Gear on 31.03.09.<br />

• Unit synchronized on 06/04/09.<br />

• Coal firing done on 15.04.09.<br />

• Unit achieved full load on 8.10.09.<br />

• Unit declared on COD w.e.f 28.01.10.<br />

Date of Main Plant Order : Placed on BHEL on 27.07.05.<br />

- 85 -<br />

Critical<br />