Sl.<br />

No<br />

Project Details<br />

Capacity<br />

(MW)<br />

PROJECTS INCLUDED IN 11 TH PLAN<br />

I<br />

PROJECTS UNDER CONSTRUCTION<br />

3<br />

Commissioning Schedule<br />

Original Actual(A)/ As<br />

now Expected<br />

Syn. COD Syn. COD<br />

Barsingsar lignite TPP<br />

(Distt – Bikaner)<br />

250<br />

U-1 125 09/08 12/08 10/09(A) 06/10<br />

11/08 06/10(A)<br />

U-2 125 03/09 06/09 06/10(A) 08/10<br />

05/09 07/10<br />

Date of Sanction 12/04<br />

Sanctioning <strong>Authority</strong> CCEA<br />

Est. Approved Cost: Rs. 111418lakhs<br />

Latest Est.Cost: Rs. 162609 lakhs<br />

Exp.during 2005-06 Rs 9626 lakhs.<br />

Exp.during 2006-07 Rs 19255 lakhs.<br />

Exp.during 2007-08 Rs 44056 lakhs.<br />

Exp.during 2008-09 Rs 42831 lakhs.<br />

Exp.during 2009-10 Rs 25086 lakhs.<br />

Exp.during 2010-11<br />

(upto )<br />

Rs -- lakhs<br />

Type of Fuel Lignite<br />

Fuel linkage 2.10 MTPA from Barsingsar lignite mine<br />

Date of Main Plant Order 29.12.2005 on BHEL<br />

Power Evacuation<br />

- 29 -<br />

Broad Status<br />

M/s Tata Consulting Engineers,<br />

Bangalore, have been selected as the<br />

project consultant.<br />

Unit-1<br />

a) Boiler erection commenced in<br />

March’07.<br />

b) Boiler drum lifted on 21 st Jun’07.<br />

c) Boiler hydro test completed on 11 th<br />

Aug’08.<br />

d) Boiler light-up is completed on 15 th<br />

Sep’09.<br />

e) TG erection commenced in July’08.<br />

f) TG box-up completed on<br />

15.04.09.<br />

g) Unit synchronized on 27 th Oct’09.<br />

h) Lignite firing is completed on<br />

29.12.09 and full load achieved on<br />

28.06.10.<br />

Unit-2<br />

a) Boiler erection commenced in<br />

May’07. 9480 MT boiler &ESP<br />

material erected out of 14555 MT.<br />

b) Boiler drum lifted on 14 th Sept’07.<br />

c) Boiler Hydraulic test completed on<br />

1 st June’09.<br />

d) Boiler light-up completed on<br />

10.02.10.<br />

e) TG box-up completed, oil flushing is<br />

completed. Steam blowing is in<br />

progress.<br />

i) Unit synchronized on 5 th Jun’10.<br />

Critical<br />

Areas