BROAD STATUS OF THERMAL POWER PROJECTS IN UTTAR PRADESH<br />
Capacity<br />
(MW)<br />
Commissioning Schedule<br />
Original Actual (A) / As<br />
Sl. Project Details<br />
Broad Status<br />
No.<br />
now Expected<br />
Syn. COD Syn. COD<br />
(Com.)<br />
PROJECTS INCLUDED IN 11<br />
(Com.)<br />
TH PLAN<br />
A. PROJECT COMMISSIONED -Nil-<br />
B. PROJECT UNDER CONSTRUCTION<br />
STATE SECTOR<br />
1. Parichha TPS Extn. 500<br />
a) BTG contract has been placed on M/s<br />
Stage-II<br />
BHEL on 28.06.2006.<br />
UPRVUNL<br />
b) Chimney: (M/s NBCC) 215 m Chimney<br />
(Distt. Jhansi )<br />
Shell completed on 22.10.09. Flue cans<br />
Unit-5<br />
250 04/09 07/09 * * fabrication & erection completed in<br />
06/09<br />
April, 10.<br />
CHIMNEY CLLAPSED<br />
Unit-6<br />
250 08/09 11/09 * * VRTICALLY ON 24.05.10.<br />
10/09<br />
Commissioning activities affected<br />
Date of approval by State Govt.<br />
Est. approved cost Rs. 190000 lakhs<br />
Latest Est. Cost Rs.235600 lakhs<br />
Exp. upto 2006-07 Rs.22599 lakhs<br />
Exp. upto 2007-08 Rs39227 lakhs<br />
Exp. upto 2008-09 Rs.65614 lakhs<br />
Exp. upto 2009-10 Rs.20881 lakhs (Sept, 09)<br />
Type of fuel Coal<br />
Fuel Linkage<br />
Date of main plant order 28.06.2006 on BHEL (BTG) at<br />
Rs.122400 Lakhs.<br />
(Zero Date: 23.02.2007)<br />
Power Evacuation system<br />
* These activities are to rescheduled<br />
after the availability of<br />
new chimney.<br />
- 47 -<br />
c) Switchyard:(M/s Areva T&D India ltd)<br />
d) Station transformer placed on<br />
foundation. Back charging byb end<br />
December, 09<br />
e) Excavation in CW system of inlet/outlet<br />
water channel area is in progress. Raft<br />
completed in CW pump house area.<br />
f) IDCT: Super structure work of IDCT is<br />
in progress.<br />
g) Civil work of Fuel oil handling system<br />
is in progress.<br />
Unit-5:<br />
a) Boiler erection started on 25.02.08. A<br />
total of 5389 MT boiler & 5051 MT<br />
ESP erection completed till 09/09.<br />
a) 13181 nos. joints completed till 09/09.<br />
b) Boiler Drum Lifted on 5.9.08.<br />
c) Boiler Hydro test conducted on<br />
31.03.09.<br />
d) Boiler light up depends upon the<br />
completion of new chimney.<br />
e) TG: Condenser erection started on<br />
20.06.09 & TG erection commenced on<br />
01.07.09. LP casing, HP Turbine, Stator<br />
placed on foundation. TG box up<br />
expected in April,10 (24.4.10)<br />
Unit-6:<br />
b) Boiler erection started on 5.05.08. A<br />
total of 5061 MT boiler & 3055 MT<br />
ESP erection completed till 09/09.<br />
c) 11945 nos. joints completed till 09/09<br />
d) Boiler drum lifted on 4.12.08.<br />
e) Boiler hydro test conducted on 16.11.09<br />
f) Boiler light up depends upon the<br />
completion of new chimney.<br />
g) Condenser & TG erection commenced<br />
in October, 09<br />
Critical<br />
Areas<br />
-<br />
Construction<br />
of new<br />
Chimney