Sl.<br />
No.<br />
3.<br />
4.<br />
PROJECT DETAILS<br />
Paras TPS Expansion<br />
(Distt. Akola)<br />
MSPGCL<br />
Uni-2<br />
Capacity<br />
(MW)<br />
250<br />
250<br />
Commissioning Schedule<br />
Original Actual(A) / As<br />
Syn.<br />
(com.)<br />
now Expected<br />
COD Syn.<br />
(com.)<br />
COD<br />
06/09 10/09 11/09(A)<br />
(09/09) 03/10(A)<br />
Date of TEC<br />
: Not Required<br />
Date of Approval by State<br />
Govt.<br />
: 12.05.06<br />
Est.Proj. cost. : 122400 Lakhs<br />
Exp. During 2006-07 : Rs.13670Lakhs<br />
Exp. during 2007-08 : Rs.30670 Lakhs<br />
Exp. during 2008-09 : Rs.54650 Lakhs<br />
Exp. during 2009-10 (Upto<br />
02/10)<br />
: Rs.20069 Lakhs<br />
Total Exp. (Upto 02/10) : Rs. 119059Lakhs<br />
Type of fuel : Coal<br />
- 73 -<br />
07/10<br />
Fuel Linkage : 2.4Million metric tones/ annum<br />
from WCL coal mines at Waghoda<br />
& Durgapur.<br />
Financial closure : Achieved in 3/06<br />
Equity: GO Maharashtra Rs245<br />
crs.<br />
Loan : PFC Rs. 888Crs.<br />
Date of Main Plant Order : M/S BHEL on 31.08.06<br />
(BTG +Electrical)<br />
Power Evacuation System: Existing 400kV line.<br />
New Parli TPP<br />
(Distt. Beed)<br />
MSPGCL<br />
250<br />
Uni-2 250 02/09<br />
03/09<br />
Date of TEC : Not Required<br />
Date of Approval by State<br />
Govt.<br />
: 12.05.06<br />
Est.Proj. cost. : 109100 Lakhs<br />
Exp. During 06-07 : Rs.11670 Lakhs<br />
Exp. During 07-08 : Rs.29480 Lakhs<br />
Exp. During 08-09 :Rs.49100 Lakhs<br />
Exp. During 09-10<br />
(Upto 02/10)<br />
Cumulative Exp.<br />
( Up to 02/10)<br />
Type of fuel :Coal<br />
:Rs.13990 Lakhs<br />
:Rs. 104240 Lakhs<br />
05/09 11/09(A) 07/10<br />
02/10(A)<br />
Financial closure : Achieved on 03.01.06<br />
Equity : GO Maharashtra Rs218<br />
Crs.Loan : PFC Rs. 830Crs.<br />
Zero date : 31.08.06<br />
Date of Main Plant Order<br />
: M/S BHEL on 31.08.06<br />
(BTG +Electrical)<br />
Unit-2<br />
Broad Status<br />
Oil synch. achieved on<br />
30.11.09.Coal firing achieved on<br />
18.02.10.Full load achieved on<br />
27.03.10.<br />
Unit-2<br />
Syn. Achieved on 12.11.09.Coal<br />
firing completed on 02.01.10.Unitcommissioned<br />
on 10.02.10.<br />
Critical<br />
Areas