Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Sl.<br />
No.<br />
Project Details<br />
PRIVATE SECTOR<br />
1. Sterlite TPP.<br />
(M/s Sterlite Energy<br />
Ltd.)<br />
Distt : J/harsuguda.<br />
First Unit (Unit-2)<br />
Second unit (Unit-1)<br />
Unit-3<br />
Unit-4<br />
Financial Closure :<br />
Estimated Cost :<br />
Exp. during 2004-05<br />
2005-06<br />
2006-07<br />
2007-08<br />
2008-09<br />
2009-10<br />
Type of fuel :<br />
Date of main plant order :<br />
BROAD STATUS OF THERMAL POWER PROJECTS IN ORISSA<br />
Capacity<br />
(MW)<br />
2400<br />
600<br />
600<br />
600<br />
600<br />
Syn.<br />
Comm<br />
Commissioning Schedule<br />
Original Actual(A)/ As<br />
12/08<br />
01/09<br />
03/09<br />
04/09<br />
06/09<br />
07/09<br />
09/09<br />
10/09<br />
now Expected<br />
COD Syn.<br />
Comm<br />
COD<br />
02/09<br />
05/09<br />
08/09<br />
11/09<br />
Achieved in 12/2008.<br />
Rs. 766900 lakhs<br />
08/10<br />
08/10<br />
12/10<br />
12/10<br />
04/11<br />
04/11<br />
08/11<br />
08/11<br />
Rs 228 lakhs<br />
Rs. 118 lakhs<br />
Rs.60582 lakhs<br />
Rs.94771 lakhs<br />
Rs.249567 lakhs<br />
Rs 94513 lakhs (up to 08/09)<br />
Coal<br />
- 100 -<br />
09/10<br />
01/11<br />
05/11<br />
09/11<br />
10.05.2006 , EPC contract on M/s<br />
Shangdong Electric Power-<br />
Corp. ( SEPCO-III) –China<br />
Boiler Supplier: Harbin Boilers, China<br />
TG Supplier: Dong fang, China<br />
Broad Status<br />
a) Full 461 acres of land required for<br />
plant facility had been acquired, 633<br />
acres of land required for Ash Pond<br />
is in advanced stage of acquisition.<br />
b) NOC received from Orissa Pollution<br />
Control Board on 21.09.2006.<br />
MOEF clearance received on<br />
07.12.2007.<br />
c) Applied for coal linkage to MOC<br />
but allocation not yet received.<br />
d) EPC contract awarded to SEPCO-<br />
III. Advance of Rs 56300 Lakhs<br />
paid for all the 4 units. Contractor<br />
had mobilized at site and started<br />
pre- construction activities.<br />
e) First Unit (Unit-2): Boiler drum<br />
lifted on 02.03.2008. Boiler Hyd.<br />
Test completed on 28.07.09. TG box<br />
up completed. BLU completed on<br />
26.06.10. CT ready in all respects.<br />
f) Second unit (Unit-1): Boiler drum<br />
lifted on 26.04.08. TG Box-up<br />
completed. CT shell casting<br />
completed. HT completed. BLU<br />
expected in 08/10.<br />
g) Unit-3: Boiler drum lifted on<br />
09.06.2008. HT completed. CT shell<br />
casting completed.<br />
h) Unit-4: Boiler drum lifted on<br />
23.11.2008. HT expected in 08/10.<br />
CT shell casting completed.<br />
i) Civil work in CHP area is in<br />
progress.<br />
j) Switchyard erection of all<br />
equipments for Unit-2 completed.<br />
ICT-1 testing completed. Erection of<br />
equipments for other units in<br />
progress.<br />
k) Chimney: shell casting completed<br />
for both chimneys. Flue can<br />
erection for first & second units<br />
completed. Work is in progress for<br />
other units.<br />
l) Double circuit from CPP to<br />
Budipada station ready for<br />
evacuation of power from first unit<br />
into state grid.<br />
Critical<br />
Areas<br />
Land<br />
acquisition<br />
for ash<br />
pond.<br />
-Letter of<br />
use for<br />
water from<br />
State Govt.<br />
for Unit-<br />
3&4<br />
Developme<br />
nt of coal<br />
block for<br />
unit-2.<br />
The issue<br />
of E -<br />
VISA to<br />
the SEPCO<br />
III / OEM’s<br />
(Original<br />
Equipment<br />
Manufactur<br />
ers)<br />
persons