Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Sl.<br />
No.<br />
4.<br />
1<br />
Project Details<br />
Bakreswar TPS Extn.<br />
(West Bengal Power<br />
Development Corpn.<br />
Ltd.) Dist. : Birbhum<br />
Unit-4*<br />
Unit-5<br />
Date of Sanction<br />
Original Approved Cost<br />
Latest Est. Cost<br />
Expenditure Up to Mar’07<br />
Expenditure during 2007-08<br />
2008-09<br />
(Upto<br />
25.07.08)<br />
Capacity<br />
(MW)<br />
420<br />
210<br />
210<br />
Syn.<br />
Comm<br />
03/07<br />
06/07<br />
06/07<br />
09/07<br />
Type of Fuel : Coal<br />
Commissioning Schedule<br />
Original Actual(A)/As<br />
07/07<br />
10/07<br />
: N.A.<br />
: Rs 152300 Lakhs<br />
: Rs 210000 Lakhs<br />
: Rs 117000 Lakhs<br />
Rs.50500 Lakhs<br />
: Rs.2000 Lakhs.<br />
Funding : JBIC, Japan<br />
now expected<br />
COD Syn.<br />
Comm<br />
COD<br />
12/07(A)<br />
03/09(A)<br />
06/09<br />
- 104 -<br />
3/09(A)<br />
6/09(A)<br />
Date of Main Plant Order : 30/11/04 (M/s ITOCHU, Japan for<br />
Steam Turbine & Gen. Transformers<br />
and M/s BHEL for Boiler & its<br />
Auxiliaries, Generators, Condensers,<br />
Ash Handling System, Water Systems<br />
etc.)<br />
PRIVATE SECTOR<br />
BUDGE-BUDGE TPS<br />
Extn.<br />
(M/S CESC Ltd..)<br />
Dist. : South Paraganas.<br />
250<br />
Unit-3 250 04/09<br />
05/09<br />
Estimated cost. :Rs. 106800 Lakhs<br />
Expend. During 05-06 : Rs.109 lakhs<br />
Expend. During 06-07 : Rs.9686 lakhs<br />
Expend. During 07-08 : Rs.18063 lakhs<br />
Expend. During 08-09 : Rs.42410 lakhs<br />
Expend. During 09-10 : Rs.4387 lakhs<br />
(up to 28.07.09)<br />
06/09<br />
Cumulative Expend. : Rs.74967 lakhs<br />
(up to 28.07.09)<br />
Type of fuel : Coal<br />
Date of Main Plant Order : 18/ 12/06 ( EPC on M/S BHEL)<br />
07/09(A)<br />
09/09(A)<br />
02/10(A)<br />
Broad Status<br />
a) Order for Boiler, its auxiliaries,<br />
Generators, Condensers, LP/HP<br />
Heaters, all power cycle piping<br />
including BFPs, CEPs, Ash<br />
Handling System and complete<br />
Raw Water, Clarified & DM<br />
Water Systems was placed on<br />
M/s BHEL on 30.11.04.<br />
b) Order for Steam Turbine,<br />
Generator Transformers, UATs,<br />
Bus Duct was placed on M/s<br />
ITOCHU Corpn. Japan on<br />
30.11.04.<br />
c) For cooling tower-2, civil works<br />
are in progress.<br />
d) Bottom Ash hopper erected. Ash<br />
slurry p/h raft completed. Ash<br />
slurry pipeline civil works in<br />
progress.<br />
Unit- 4:<br />
i) Synchronization with oil on 23 rd<br />
Dec’07. Coal firing completed on<br />
31.03.08. Full load achieved on<br />
31.03.08. COD declared w.e.f<br />
08.03.09.<br />
Unit-5:<br />
i) i) Unit synchronized (coal) on<br />
30.03.09. Full load achieved on<br />
07.06.09. COD declared on<br />
27.06.09.<br />
Critical<br />
Areas<br />
a). Main plant order (EPC contract) Signin<br />
placed on M/S BHEL on 18.12.2006 g<br />
for contractual value of Rs 854 Crs. of FSA<br />
excluding switch yard and chimney.<br />
b). Switch yard : Order has been placed<br />
on M/S Siemens Ltd on 03.01.2007<br />
c). Boiler erection started on 10.08.2007.<br />
Boiler drum lifted in 02/08. Hydro<br />
Test completed on 29.09.08. BLU<br />
completed on 19.03.09. Steam<br />
blowing operations started on<br />
01.06.09.<br />
d). Coal synchronization with 2 mills was<br />
completed on 03.08.09.<br />
e). Full load achieved on 29/09/09.<br />
f). COD achieved w.e.f 28.02.10.