Sl.<br />

No.<br />

4.<br />

1<br />

Project Details<br />

Bakreswar TPS Extn.<br />

(West Bengal Power<br />

Development Corpn.<br />

Ltd.) Dist. : Birbhum<br />

Unit-4*<br />

Unit-5<br />

Date of Sanction<br />

Original Approved Cost<br />

Latest Est. Cost<br />

Expenditure Up to Mar’07<br />

Expenditure during 2007-08<br />

2008-09<br />

(Upto<br />

25.07.08)<br />

Capacity<br />

(MW)<br />

420<br />

210<br />

210<br />

Syn.<br />

Comm<br />

03/07<br />

06/07<br />

06/07<br />

09/07<br />

Type of Fuel : Coal<br />

Commissioning Schedule<br />

Original Actual(A)/As<br />

07/07<br />

10/07<br />

: N.A.<br />

: Rs 152300 Lakhs<br />

: Rs 210000 Lakhs<br />

: Rs 117000 Lakhs<br />

Rs.50500 Lakhs<br />

: Rs.2000 Lakhs.<br />

Funding : JBIC, Japan<br />

now expected<br />

COD Syn.<br />

Comm<br />

COD<br />

12/07(A)<br />

03/09(A)<br />

06/09<br />

- 104 -<br />

3/09(A)<br />

6/09(A)<br />

Date of Main Plant Order : 30/11/04 (M/s ITOCHU, Japan for<br />

Steam Turbine & Gen. Transformers<br />

and M/s BHEL for Boiler & its<br />

Auxiliaries, Generators, Condensers,<br />

Ash Handling System, Water Systems<br />

etc.)<br />

PRIVATE SECTOR<br />

BUDGE-BUDGE TPS<br />

Extn.<br />

(M/S CESC Ltd..)<br />

Dist. : South Paraganas.<br />

250<br />

Unit-3 250 04/09<br />

05/09<br />

Estimated cost. :Rs. 106800 Lakhs<br />

Expend. During 05-06 : Rs.109 lakhs<br />

Expend. During 06-07 : Rs.9686 lakhs<br />

Expend. During 07-08 : Rs.18063 lakhs<br />

Expend. During 08-09 : Rs.42410 lakhs<br />

Expend. During 09-10 : Rs.4387 lakhs<br />

(up to 28.07.09)<br />

06/09<br />

Cumulative Expend. : Rs.74967 lakhs<br />

(up to 28.07.09)<br />

Type of fuel : Coal<br />

Date of Main Plant Order : 18/ 12/06 ( EPC on M/S BHEL)<br />

07/09(A)<br />

09/09(A)<br />

02/10(A)<br />

Broad Status<br />

a) Order for Boiler, its auxiliaries,<br />

Generators, Condensers, LP/HP<br />

Heaters, all power cycle piping<br />

including BFPs, CEPs, Ash<br />

Handling System and complete<br />

Raw Water, Clarified & DM<br />

Water Systems was placed on<br />

M/s BHEL on 30.11.04.<br />

b) Order for Steam Turbine,<br />

Generator Transformers, UATs,<br />

Bus Duct was placed on M/s<br />

ITOCHU Corpn. Japan on<br />

30.11.04.<br />

c) For cooling tower-2, civil works<br />

are in progress.<br />

d) Bottom Ash hopper erected. Ash<br />

slurry p/h raft completed. Ash<br />

slurry pipeline civil works in<br />

progress.<br />

Unit- 4:<br />

i) Synchronization with oil on 23 rd<br />

Dec’07. Coal firing completed on<br />

31.03.08. Full load achieved on<br />

31.03.08. COD declared w.e.f<br />

08.03.09.<br />

Unit-5:<br />

i) i) Unit synchronized (coal) on<br />

30.03.09. Full load achieved on<br />

07.06.09. COD declared on<br />

27.06.09.<br />

Critical<br />

Areas<br />

a). Main plant order (EPC contract) Signin<br />

placed on M/S BHEL on 18.12.2006 g<br />

for contractual value of Rs 854 Crs. of FSA<br />

excluding switch yard and chimney.<br />

b). Switch yard : Order has been placed<br />

on M/S Siemens Ltd on 03.01.2007<br />

c). Boiler erection started on 10.08.2007.<br />

Boiler drum lifted in 02/08. Hydro<br />

Test completed on 29.09.08. BLU<br />

completed on 19.03.09. Steam<br />

blowing operations started on<br />

01.06.09.<br />

d). Coal synchronization with 2 mills was<br />

completed on 03.08.09.<br />

e). Full load achieved on 29/09/09.<br />

f). COD achieved w.e.f 28.02.10.