Sl.<br />

No.<br />

BROAD STATUS OF CENTRAL SECTOR THERMAL POWER PROJECTS<br />

(DAMODAR VALLEY CORPORATION)<br />

PROJECT DETAILS<br />

A PROJECTS INCLUDED IN 11 TH PLAN<br />

Capacity<br />

(MW)<br />

Commissioning Schedule<br />

Original Actual(A) / As now<br />

Expected<br />

Syn. COD Syn. COD<br />

(Comm)<br />

(Comm)<br />

I PROJECTS COMMISSIONED. 1000 MW<br />

1.<br />

Mejia TPS Ph-I<br />

(Distt. Bankura, West Bengal)<br />

Unit-5<br />

Unit-6*<br />

500<br />

250<br />

250<br />

11/06<br />

01/07<br />

Investment approval : 18.02.2009 (DVC Board)<br />

Revised Estimated cost : Rs.236663 lakhs<br />

Exp. During 2004-05 : Rs 29883.34 Lakhs<br />

Cumul. Exp. 2004-05 : Rs. 29906.34 Lakhs<br />

Exp. During 2005-06 : Rs 50163 Lakhs<br />

Cumul. Exp. 2005-06 : Rs 80069.34 lakhs<br />

Exp. During 2006-07 : Rs 84979.94 lakhs<br />

Cumul. Exp. 2006-07 : Rs 165049.28 lakhs<br />

Exp. During 2007-08 : Rs 37248 lakhs<br />

Cumul. Exp. 2007-08 : Rs 202297.28 lakhs<br />

Exp. in 2008-09 : Rs 13000 lakhs<br />

Cumul.Exp. in 2008-09 : Rs 215297.28 lakhs<br />

01/07<br />

03/07<br />

Exp. in 2009-10 : Rs 1152.00 lakhs<br />

Cumulative exp. : Rs. 216449.28 lakhs (Jan’10)<br />

Type of fuel : Coal<br />

2.<br />

Date of Main Plant Order: 15.06.04 on M/s BHEL(EPC)<br />

Chandrapura TPS<br />

500<br />

(Distt. Bokaro Jharkhand)<br />

Unit -7<br />

250 11/06<br />

12/06<br />

01/07<br />

Unit -8<br />

250 01/07<br />

02/07<br />

03/07<br />

Investment approval. : 09.06.2004 (DVC Board)<br />

30/03/07 (A)<br />

02/01/08 (A)<br />

01/10/07(A)<br />

22/05/08(A)<br />

06.01.09(A)<br />

04.11.09(A)<br />

30.03.10(A)<br />

31.03.10(A)<br />

- 30 -<br />

29/02/08 (A)<br />

24/09/08 (A)<br />

08/10<br />

09/10<br />

Estimated cost : Rs.206645 lakhs<br />

Revised Estimated cost : Rs.220135 lakhs<br />

Exp. During 2004-05 : Rs 26561.00 Lakhs<br />

Cumul. Exp. 2004-05 : Rs. 26561.00 Lakhs<br />

Exp. During 2005-06 : Rs 39162.00 Lakhs<br />

Cumul. Exp. 2005-06 : Rs 65723.00 lakhs<br />

Exp. During 2006-07 : Rs 58811.00 Lakhs<br />

Cumul. Exp. 2006-07 : Rs 124534.00 lakhs<br />

Exp. During 2007-08 : Rs 46306.00 Lakhs<br />

Cumul. Exp. 2007-08 : Rs 170840.00 lakhs<br />

Exp. During 2008-09 : Rs 29422.00 Lakhs<br />

Cumul. Exp. 2008-09 : Rs 200262.00 Lakhs<br />

Exp. During 2009-10 : Rs 21718.00 Lakhs<br />

Cumul. Exp. 2009-10 : Rs 221980.00 Lakhs (Jan_10)<br />

Date of Main Plant Order : 30.06.04 on M/s BHEL (Turnkey)<br />

Type of fuel : Coal<br />

Power Evacuation System:<br />

1) 220 KV D/C LILO of CTPS-MTPS at Kalyaneshwari CKT-I (89 Ckm) & CKT-<br />

II(90 Ckm).<br />

2) 220 KV D/C LILO of Kalyaneshwari- Pithakyari Line (8 Ckm X 2 ).<br />

Fuel Supply Arrangement:<br />

2.0 MTPA Coal from Gondulpara, CCL, Coal block jointly allocated to TVNL &<br />

DVC on 50:50 basis from 2013-14 and before this CCL will supply 2.08 MTPA coal.<br />

Broad Status<br />

Unit-5:<br />

Unit synchronized on 30.03.07.Coal<br />

firing achieved on 24.11.07, full load<br />

achieved on 2 nd Jan’08 and declared<br />

on commercial operation since 29<br />

Feb’08.<br />

Unit-6*:<br />

Unit Synchronised on<br />

01.10.2007. Coal firing achieved on 30<br />

Mar’08. Full load achieved on<br />

22.05.2008. Unit declared for<br />

commercial operation since 24<br />

Sep’08.<br />

* Unit slipped from 10 th Plan.<br />

Unit-7<br />

Unit synchronized on 06.01.09.Coal<br />

firing was achieved on 15 Sep’09 with<br />

the alternative (contingency) route.<br />

The Unit commissioned (Full load) on<br />

04.11.09 at 17:48 Hrs. Unit COD is<br />

expected in August’10.<br />

Unit-8<br />

BOILER<br />

Boiler Erection commenced on<br />

31.01.2006. Boiler drum was lifted<br />

on 14.08.2006. Hydraulic test<br />

(Drainable) completed on 02 nd<br />

Novomber’07.The Boiler Lightup<br />

done on 29.11.09 at 20.30 Hrs.. SBO<br />

completed on 10 th Mar’10. TG<br />

erection started on 05.08.08 and TG<br />

box up was completed in Nov’09.<br />

Steam rolling was completed in<br />

Mar’10.<br />

Unit was oil synchronised on<br />

30.03.10. Unit achieved coal firing<br />

and full load on 31.03.2010. Unit<br />

COD is expected in Sep’10.<br />

Critical<br />

Areas<br />

Completion<br />

of Coal<br />

Handling<br />

Plant.<br />

Completion<br />

of Heavy<br />

oil & PT<br />

plant.<br />

Repair of<br />

damaged<br />

rotor of<br />

unit-7