Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Sl. No<br />
PROJECT DETAILS<br />
Capacity<br />
(MW)<br />
Commissioning Schedule<br />
Original Actual(A) / As<br />
now Expected<br />
Syn. COD Syn. COD<br />
(Comm) (Comm)<br />
III. DVC & Tata Power, Joint Venture under Public Private Partnership programme:<br />
1.<br />
Maithon R/B TPP<br />
(MPL – a JV Co. of DVC<br />
& Tata Power), PO-Nirsa<br />
Distt. Dhanbad, Jharkhand<br />
Unit-1<br />
1050<br />
525<br />
09/10<br />
10/10<br />
Unit-2 525 03/11<br />
04/11<br />
Est. cost<br />
(Based on A.P. 07-08)<br />
Type of fuel : Coal<br />
Main Plant Order(EPC) on BHEL : 25.10.2007<br />
12/10<br />
06/11<br />
01/11<br />
03/11<br />
05/11<br />
07/11<br />
: Rs. 445500 lakhs (DVC contr.-34710)<br />
Exp. During 2006-07 : Rs 1649.87 Lakhs<br />
Cumul. Exp. 2006-07 : Rs 1649.87 Lakhs<br />
Exp. During 2007-08 : Rs 35433.96 Lakhs<br />
Cumul. Exp. 2007-08 : Rs 37083.83 lakhs<br />
Exp. During 2008-09 : Rs 68350.00 Lakhs<br />
Cumul. Exp. 2008-09 : Rs 105433.83 Lakhs<br />
Exp. During 2009-10 : Rs 105007.00 Lakhs<br />
Cumul. Exp.2009-10 : Rs 207882.83 Lakhs (Jan_10)<br />
Power Evacuation System:<br />
a) Open access by PGCIL for evacuation and startup power.<br />
Fuel Supply Arrangement:<br />
a) SLC (LT) granted long term linkage for 4.864 MTPA for BCCL.<br />
b) MT(0.5 MT each from Karo OCP & Khasmahal OCP) from CCL<br />
c) MT out of middling from Tata Steel<br />
Zero date of the project : 25.10.2007 (BTG ORDER)<br />
- 36 -<br />
05/11<br />
08/11<br />
Broad Status<br />
(i) DVC Board on 24.03.05 ratified the ownership<br />
pattern of 26% (DVC) and 74% (TPC)<br />
Status:<br />
(i) Boiler erection of unit-1 was started on<br />
08.09.2008 against the schedule of 25.08.2008<br />
and 11477 MT material erected so far. Drum<br />
lifted on 22.03.09. Boiler hydro test completed<br />
on 24th Mar’10. Boiler litup is expected in<br />
Aug’10<br />
(ii) TG deck casting was completed on<br />
21.06.2009.Condenser erection work started on<br />
10.08.09. TG erection started on Dec’09.<br />
Preliminary works for Turbine and Stator<br />
erection are in progress. condenser tube<br />
insertion is in progress. TG boxup is expected<br />
in Sep’10.<br />
(iii) For Unit-2, Boiler erection started in 21 Jan’09<br />
and 7284 MT material erected so far. Drum<br />
lifted on 03.08.09. Boiler hydro test is expected<br />
in Aug’10.<br />
(iv) TG raft casting is completed. Shuttering for<br />
columns is in progress. Deck casting completed<br />
27.12.09.condenser erection work started on<br />
23.06.10.<br />
(v) ESP erection work of unit-1& 2 started and<br />
3381 & 3106 MT material has been erected so<br />
far respectively.<br />
(vi) Power House PH#1 structural work has been<br />
almost completed .erection work of Unit-2<br />
started and 1829 MT materials have been<br />
erected so far.<br />
(vii) Chimney – Flue can erection work is in<br />
progress.<br />
(viii) Cooling Tower(IDCT1) – Trial Run of IDCT1<br />
has been completed. Mechanical equipment<br />
erection and film filling work for IDCT2 is in<br />
progress.<br />
(ix) DM plant has been partially commissioned.<br />
Piping work for pumps & installation of Field<br />
instruments is in progress.<br />
(x) CHP: RCC work at Track hopper is in progress.<br />
Mechanical Erection for Stacker Reclaimer has<br />
commenced. Structural work for Crusher House<br />
has commenced. Junction Tower and Conveyor<br />
Belt related structural erection is in progress.<br />
Manufacturing is in progress for CHS related<br />
equipment.<br />
(xi) Switch yard etc- Testing for 400kV equipment<br />
has been completed. Testing of Control and<br />
relay panel I in progress. Testing of reactors<br />
and Station Transformer is in progress.<br />
Illumination work is in progress at Power House<br />
#1. Earthing Material laying work is in<br />
progress. HVAC equipment installation has<br />
been completed in Switchyard Control Room.<br />
(xii) Project has achieved 81.53% progress.<br />
Critical<br />
Areas<br />
Timely<br />
supply of<br />
turbines.