Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Sl.<br />
No.<br />
2.<br />
Project Details<br />
Harduaganj TPS Extn.<br />
UPRVUNL<br />
(Distt. Aligarh )<br />
Capacity<br />
(MW)<br />
500<br />
Commissioning Schedule<br />
Original Actual (A) /<br />
As now<br />
Syn.<br />
(Com.)<br />
Expected<br />
COD Syn.<br />
(Com.)<br />
COD<br />
Unit-8 250 08/09 10/09 2/11 03/11<br />
09/09<br />
03/11<br />
Unit-9 250 12/09 02/10 03/11 04/11<br />
01/10<br />
04/11<br />
Date of approval by State Govt.<br />
Est. approved cost Rs. 190000 lakhs<br />
Latest Est. Cost Rs. 222500 lakhs<br />
Cumm. Exp. upto 2006-07 Rs. 16472.41 lakhs<br />
Exp. during 2007-08 Rs. 24920 lakhs<br />
Exp. during 2008-09 Rs.58955 lakhs<br />
Exp. during 2009-10 Rs53937 lakhs<br />
Type of fuel Coal<br />
Fuel linkage 1.943 MTPA of coal allotted by MOC<br />
from CCL vide MOC lr. no. 23011/ 87/<br />
2005/ CPD , dated 2.8.06 and CCL<br />
lr.no.<br />
8.9.06.<br />
CGM/PP/06/2/233-37 dated<br />
Date of main plant order<br />
28.06.2006 on BHEL (BTG) at<br />
Rs.122400 Lakhs.<br />
Power Evacuation Existing 220 kV lines are sufficient<br />
for cater the load of these two units.<br />
- 48 -<br />
Broad Status<br />
• Zero date of the project is 07.09.06.<br />
• Site handed over to M/s BHEL on 29 th<br />
March’07.<br />
• UPRVUNL informed that on 19 th<br />
May’09 a major disaster happened at the<br />
site i.e. complete main plant building<br />
structure main column (A1to A9 in A<br />
row),(B1 to B9 in B row), roof<br />
truss(2to9), Crane Girder 2to9 of A row<br />
& 1to9 of B row of Unit-8 being erected<br />
by the sub-contractor of M/s BHEL<br />
collapsed. After this major mishap all the<br />
damaged columns are required to be<br />
fabricated and erected which may cause<br />
delay in readiness of TG hall .<br />
• Unit-9 will be commissioned prior to<br />
unit-8<br />
BOPs:<br />
• Order for Chimney has been placed on M/s<br />
NBCC on 1 st Jun’07. Raft reinforcement &<br />
PCC is in progress .<br />
• Structural steel fabrication & erection is in<br />
progress.<br />
• PCC work of wagon Tippler-1&2 in<br />
progress. Raft reinforcement for TP-1 is in<br />
progress..<br />
• AHP contractor yet to mobilize to start<br />
works.<br />
• DM tank foundation completed.<br />
• Excavation in Cooling Tower area in<br />
progress.<br />
Unit-8:<br />
• Boiler erection commenced on 25 th Aug’08.<br />
4589 MT material erected till 05/09. 2835<br />
MT ESP material erected .<br />
• Boiler drum lifting completed on 25/01/09.<br />
• Boiler hydraulic test is expected by<br />
October, 09<br />
• ESP: Collecting electrodes erection in<br />
pass-A completed Hoppers erection is in<br />
progress Electrode supporting structure<br />
erection in Pass-B in progress.<br />
• FD fan & ID fans foundation is in progress.<br />
• TG deck RCC columns & Beams casting in<br />
progress.<br />
• Condenser erection expected to start after<br />
completion of erection of damaged columns<br />
of AB row<br />
Unit-9:<br />
• Boiler erection commenced on 20.11.08 and<br />
is in progress.790 MT boiler material and<br />
255 MT ESP material erected.<br />
• Boiler drum lifting completed on 31/03/09.<br />
• Boiler hydraulic test is expected by Nov’09.<br />
• Boiler light up is expected in April, 2009.<br />
• TG deck construction in progress and TG<br />
erection is likely to commence in<br />
December, 2009.<br />
• Commissioning is expected in 09/2010<br />
Critical<br />
Areas<br />
1-<br />
Erection<br />
of<br />
Turbine<br />
2- Raw<br />
Water<br />
Pump<br />
House<br />
3- Ash<br />
Handling<br />
System