BROAD STATUS OF CENTRAL SECTOR THERMAL POWER PROJECTS<br />

NATIONAL THERMAL POWER CORPORATION<br />

Sl.<br />

Capacity Commissioning Schedule<br />

No. PROJECT DETAILS (MW) Original Actual(A) / As<br />

now Expected<br />

Broad Status<br />

Syn. COD Syn. COD<br />

(com.)<br />

PROJECTS INCLUDED IN 11<br />

(com)<br />

TH PLAN<br />

I. PROJECTS COMMISSIONED<br />

1. Ratnagiri CCPP 1480<br />

M/sRatnagiri Gas<br />

The erstwhile Dabhol CCPP Ph-II was to<br />

&Power Pvt.Ltd.<br />

be synchronized during the year 2001-02<br />

(Erstwhile Dabhol<br />

but due to rift between MSEB and DPC,<br />

CCGT Ph II )<br />

the construction work of Phase-II<br />

(Distt. Ratanagiri)<br />

terminated since June 17, 2001. Since the<br />

Block-II (2GT+1ST) 2x240+ 05/06 CTG2A-4/06(A) dispute has been resolved and a new<br />

260 CTG2B-5/06(A) Company Ratnagiri Gas and Power<br />

STG2X-.5/06(A) Pvt.Ltd. has been constituted with M/S<br />

Block-III (2GT+1ST)* 2x240+ 01/07 CTG3A-17.06.07(A) NTPC and GAIL to revive the project.<br />

260 CTG3B-05.09.07(A) RGPPL started the revival process and<br />

STG3X-28.10.07 (A) synchronized one block of Ph-II as per the<br />

Date of TEC<br />

: 26.11.93<br />

given schedule:<br />

(After renegotiation) : (17.4.96)<br />

CTG2A-30.4.06<br />

Investment Approval -<br />

Completed cost. : US$ 1868 Mn<br />

Exp. Upto 10/99 : US$ 337 Mn<br />

Financial Closure : Achieved on 6th May, 99<br />

Exp. During 07-08 : N.A.<br />

(Upto 09/07)<br />

Type of fuel : Naphtha/LNG<br />

Date of Main Plant Order : May 1999(GTs-GE,USA, ST-GE,USA<br />

&HRSG-VOGT Power<br />

International,USA)<br />

CTG2B-14.5.06<br />

STG2X-07.5.06<br />

Block-II achieved COD w.e.f.1.9.07.<br />

Synchronization of block-III of Ph-II is<br />

planned as per the given schedule:<br />

CTG3A-17.06.07 (A)<br />

CTG3B-05.09.07 (A)<br />

STG3X-28.10.07(A)<br />

Block-III COD achieved on 21. 11.07.<br />

2. Sipat STPP St-II 1000<br />

Unit-4<br />

(Dist. Bilaspur,<br />

Unit synchronized on 27.5.07.<br />

Chhattisgarh)<br />

Coal Firing achieved on 24.10.07. Water<br />

Unit-4 * 500 06/07 09/07 05/07(A) 06/08(A) allocation approval restored. Unit re-<br />

Unit-5 * 500 12/07 03/08 08/08(A) 1/09(A) synchronized on 06.5.08. Full load<br />

Date of TEC : Not required<br />

operation achieved on 20.05.08.COD<br />

Investment Approval : N.A.<br />

achieved on 20.06.08.<br />

Completed cost. : Rs. 403967 Lakhs<br />

Unit-5<br />

Unit synchronized on 13.08.08.Coal firing<br />

Exp. Upto 03/08 : Rs 307884 Lakhs<br />

started on 10.11.08.Full Load Operation<br />

Exp. During 08-09 : Rs 8444 Lakhs<br />

achieved on 27.12.08.COD declared<br />

(Upto 08/08)<br />

w.e.f.01.01.09.<br />

Type of fuel : Coal<br />

( only 4 days trial run)<br />

Fuel Linkage : Available<br />

Date of Main Plant Order :15.12.2003 on M/s BHEL<br />

* Slipped from 10 th Plan<br />

- 13 -<br />

Critical<br />

Areas