Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
BROAD STATUS OF CENTRAL SECTOR THERMAL POWER PROJECTS<br />
NATIONAL THERMAL POWER CORPORATION<br />
Sl.<br />
Capacity Commissioning Schedule<br />
No. PROJECT DETAILS (MW) Original Actual(A) / As<br />
now Expected<br />
Broad Status<br />
Syn. COD Syn. COD<br />
(com.)<br />
PROJECTS INCLUDED IN 11<br />
(com)<br />
TH PLAN<br />
I. PROJECTS COMMISSIONED<br />
1. Ratnagiri CCPP 1480<br />
M/sRatnagiri Gas<br />
The erstwhile Dabhol CCPP Ph-II was to<br />
&Power Pvt.Ltd.<br />
be synchronized during the year 2001-02<br />
(Erstwhile Dabhol<br />
but due to rift between MSEB and DPC,<br />
CCGT Ph II )<br />
the construction work of Phase-II<br />
(Distt. Ratanagiri)<br />
terminated since June 17, 2001. Since the<br />
Block-II (2GT+1ST) 2x240+ 05/06 CTG2A-4/06(A) dispute has been resolved and a new<br />
260 CTG2B-5/06(A) Company Ratnagiri Gas and Power<br />
STG2X-.5/06(A) Pvt.Ltd. has been constituted with M/S<br />
Block-III (2GT+1ST)* 2x240+ 01/07 CTG3A-17.06.07(A) NTPC and GAIL to revive the project.<br />
260 CTG3B-05.09.07(A) RGPPL started the revival process and<br />
STG3X-28.10.07 (A) synchronized one block of Ph-II as per the<br />
Date of TEC<br />
: 26.11.93<br />
given schedule:<br />
(After renegotiation) : (17.4.96)<br />
CTG2A-30.4.06<br />
Investment Approval -<br />
Completed cost. : US$ 1868 Mn<br />
Exp. Upto 10/99 : US$ 337 Mn<br />
Financial Closure : Achieved on 6th May, 99<br />
Exp. During 07-08 : N.A.<br />
(Upto 09/07)<br />
Type of fuel : Naphtha/LNG<br />
Date of Main Plant Order : May 1999(GTs-GE,USA, ST-GE,USA<br />
&HRSG-VOGT Power<br />
International,USA)<br />
CTG2B-14.5.06<br />
STG2X-07.5.06<br />
Block-II achieved COD w.e.f.1.9.07.<br />
Synchronization of block-III of Ph-II is<br />
planned as per the given schedule:<br />
CTG3A-17.06.07 (A)<br />
CTG3B-05.09.07 (A)<br />
STG3X-28.10.07(A)<br />
Block-III COD achieved on 21. 11.07.<br />
2. Sipat STPP St-II 1000<br />
Unit-4<br />
(Dist. Bilaspur,<br />
Unit synchronized on 27.5.07.<br />
Chhattisgarh)<br />
Coal Firing achieved on 24.10.07. Water<br />
Unit-4 * 500 06/07 09/07 05/07(A) 06/08(A) allocation approval restored. Unit re-<br />
Unit-5 * 500 12/07 03/08 08/08(A) 1/09(A) synchronized on 06.5.08. Full load<br />
Date of TEC : Not required<br />
operation achieved on 20.05.08.COD<br />
Investment Approval : N.A.<br />
achieved on 20.06.08.<br />
Completed cost. : Rs. 403967 Lakhs<br />
Unit-5<br />
Unit synchronized on 13.08.08.Coal firing<br />
Exp. Upto 03/08 : Rs 307884 Lakhs<br />
started on 10.11.08.Full Load Operation<br />
Exp. During 08-09 : Rs 8444 Lakhs<br />
achieved on 27.12.08.COD declared<br />
(Upto 08/08)<br />
w.e.f.01.01.09.<br />
Type of fuel : Coal<br />
( only 4 days trial run)<br />
Fuel Linkage : Available<br />
Date of Main Plant Order :15.12.2003 on M/s BHEL<br />
* Slipped from 10 th Plan<br />
- 13 -<br />
Critical<br />
Areas